To                                                                                            Date………………..

The Engineer







Dear Sir



Request for notification of the Delegated Powers of the Engineer





With reference to Clause 2.2 of the Conditions we note that we have yet to receive written notice of the powers delegated to your representative.



You will be aware that to permit the efficient administration of the contract both the Employer and ourselves require written notice of such delegated powers as soon as possible as required by Clause 2.3 of the conditions.



In the meantime we contractually unable to accept instruction from your representative other than those in respect of supervision, testing and examination of materials and workmanship incorporated into the works and the present situation may/will disrupt the progress of the works.





Yours faithfully







……………………………………