Completion report of the administrative structure
Implementation of Smart
1-
The roof of the administrative building of the highest building
- Inspection room assembly of air-conditioning pipes The top of the administrative building was created in a random way and there is no clothes or openings for air conditioning pipes or cover for the room
- Inspection room cable assembly electricity feeder for air conditioning This room was created a replica of the rest of the assembly rooms assembled roof surface with 6 inspection rooms
- There is a network of water supply to the top of the surface was installed part of the wall of the building - suspended - and another part on the roof of the building
- There are joints in the ceiling tile
- Distribution of air conditioners on the roof All the chassis of the devices that were installed under the wider devices of the thickness of the device, which forced the installation of corners and iron rods on the chassis, which was produced and not updated and installed on the chassis
The equipment can be installed and connected to the electrical cables
2-
Fractures, cracks and separation of the walls of the building above
- The presence of cracks and fractures and separation of the walls built from the top of the main entrance to the building and the internalization of the walls from the inside
- The presence of fractures and fractures and separation of the walls of the dictator of drainage from the walls of the administrative building from the top of the surface at a distance to the bottom of the walls more than two meters down
3. External binding of the building
There is a connection at the ends of the outer binding and the center by connecting small parts to each other
3-
Fourth Floor
- Do not paint the iron fire pipes and installed the suspension ceiling on the pipelines without paint
- There are notes in the works of marble, health and ceramics, and the lack of symmetry installation of baths and non-tropical ceramic tiles in the floors and walls
4 - Drainage pits of the external administrative building and its own office buildings
- The absence of metal gates for the openings of the docket built from the bottom
- Lack of whiteness and completion of the whiteness of the inside
- Non-anchored stacks of drainage columns
- Thickness of the drainage sands
- Failure to complete the installation of the stools of the stalagmites for drainage
- The presence of water filtration from sewage pipes to the ground floor
- Separation of buildings and walls from the administrative building
- Failure to complete the installation of fire extinguishers and non-line (black pipe)'
Mohammed Drehem