The following minimum conceptual requirements
shall be applied to the machines and installations in a way to ease the
maintenance tasks as far as possible:
Gas Turbines.
Through the instruction manuals related to the maintenance schedule of the gas turbines, the Contractor is required to
carefully stipulate the scope and the frequency of the major inspections and
overhauls, particularly as regards the hot gas path components.
In addition,
the following shall be included:
Bypass Damper,
HRSG and Air Cooled Condenser
Adequate spacing in between the HRSG tube
bundles, for tube replacement, off-load water washing of and on-load soot
blowing system with retractable soot blowers to be provided. 0% Gas leakage on damper diverter is required
to ensure safe maintenance on HRSGs.
Provisions for water washing air-cooled condensers ere are required.
Accessibility
a] All equipment/components shall be arranged /
installed in such a way that each shall be easily and safely accessible for
operation and maintenance. Permanent platforms shall be provided for all the
equipment/instruments/valves etc. required to be visited during normal
operation or maintenance.
The access to the platform shall be through stairs
wherever possible. Ladders shall only be provided where space or passage
obstruction prohibits the provision of stairs, with Company / Engineer approval.
b] The equipment to be visited during long-term
maintenance (like six-monthly or annual maintenance etc) temporary
accessibility arrangement shall be provided through A-frame ladders, extendable
telescopic ladders, mobile platforms, scaffolding, etc.
The type number and size
shall be as per site requirements with Company/Engineer’s approval. At least
eight (8) sets of scaffoldings 6 m high each, with lockable wheels and other
accessories shall be provided for the plant.
c] Special means shall be provided such as sky
lifts etc. to reach the high elevation or ceiling mounted equipment like
lighting, fire detectors, etc.
d] All the outdoor/indoor equipment shall be
reachable by suitable vehicles such as trucks, vacuum trucks, fork lifters,
cranes etc. as applicable.
e] The hoses or pipes provided with temporary
pumps, vacuum trucks etc. shall be sufficient to reach the farthest equipment
required to be served.
f] All the indoor equipment must be reachable by
crane. If not, electric hoisting/lifting with electric travelling facilities
shall be provided with a travelling beam up to the point where removal by mobile
means is possible.
g] Manual hoists with travelling trolleys can be
provided where approved by the Company/Engineer. Size, type, the quantity shall be
as per Company/Engineer’s approval.
h] The outdoor equipment shall be reachable by a mobile crane. If not, special arrangements shall be made to facilitate
maintenance/dismantling and removal of such equipment with Company/Engineer’s
approval.
i] All building roofs having any equipment shall
be accessible through stairs. For the low bay roof, three access stairs shall be
provided, one at the centre and one (1) each at the end of the blocks.
Crossover bridges shall be provided on a low bay roof, if required, to ensure
that every piece of equipment is easily accessible.
j] In hazardous areas, access shall be provided on
at least two far apart locations to facilitate the emergency exit.
k] Crossover platform shall be provided, wherever
required.
l] Four (4) low bed hand trolleys shall be
provided for replacement of FM 200 cylinders.
m] In the turbine hall, a 4-meter wide passage shall
be provided throughout the length for access of vehicles, cranes, etc.
a] In general, adequate space shall be provided
for maintenance of equipment. The Contractor shall take into account the provision
of adequate space for dismantling/removal of equipment such as draw out of the tube
bundles, breakers, removal of turbine/generator rotors, HVAC equipment, etc.
b] Electrical panels, cabinets, etc. shall have
sufficient space around for the full opening of doors, maintenance, and removal if
required.
c] The arrangement of equipment shall be such that
sufficient space is available during maintenance for the laydown of parts. The
turbine hall arrangement should be on the basis of all the gas turbines of one
block under maintenance simultaneously. The Contractor shall submit a scaled
laydown drawing to demonstrate the availability of sufficient space and scheme for
laydown of components of all gas turbines together.
d] The arrangement of strainers shall be such that
strainer baskets/elements, especially the Y-strainers close to the ground can
be easily removed/replaced.
e] The equipment shall have adequate headroom to
facilitate lifting and removal, taking into account the space required for
slings and hooks of lifting equipment.
Sufficient number of utility stations for
service water and air shall be provided all over the plant for the cleaning
operation during normal running as well as overhauling/maintenance of the
equipment/component.
Each utility station shall have a quick connection
couplings, 25 m long air and water hoses with compatible couplings, on one-end
and gun type nozzles on the other end mounted on a suitable stand.
Number and
location of utility stations shall be subject to Company/Engineer’s approval.
Maintenance Space
- Air/Water Utility
Station
- Future Connections
In order to make the outages of running units
to a minimum at the time of tie-in, all the future connections shall be
provided with a valve and blind flange.
Redundancy
a] All essential equipment shall be redundant,
bypasses shall be provided to facilitate maintenance of equipment, valves etc.
without shutdown of main equipment and to prevent a single cause failure.
b] All the pumps, compressors shall be 2 x 110% or
3 x 60% to meet the redundancy requirements unless otherwise stated.
c] All filters shall be duplex type unless
otherwise stated.
- Valves
a] All control valves shall have bypasses with
isolation valves unless otherwise stated or the requirement is specifically
waived by the Company/Engineer upon specific request and satisfactory
acceptable technical justification by the Contractor.
b] All motorized or pneumatic valves shall have the facility for manual operation also.
c] Local operation facility shall be provided for
all remotely operated valves to facilitate maintenance through open/close buttons
and lockable/remote selector switch.
d] Facility shall be provided for online stroking
of all remote operated and control valves.
e] Lockable valves shall be provided wherever
required.
f] The important motorized valves, which can shut down the unit if out of service, shall have bypass valves with isolation
valves.
g] The motorized valves/pneumatic valves on fuel
lines shall have isolation valves upstream/downstream unless otherwise stated
or approved by the Company/Engineer.
h] The safety/relief valves, having common
discharge lines shall be provided with lockable isolation valves upstream of
the safety valve.
i] Critical loop actuators such as ESD, EIV etc.
shall be redundant with an online maintenance facility on the failed actuators.
Piping and Valve Lists
a] The Contractor shall submit a comprehensive
pipe list covering the whole plant containing service, identification number,
piping size, material, class/pressure rating or schedule number;
design/operating pressure and temperature etc. The list shall also indicate the electrode used for welded pipes and the type/rating of gasket used in flanged pipes.
b] A comprehensive valve list shall be submitted
covering the whole plant, indicating valve identification number, type,
service, pressure and temperature rating, material, make, operating pressure,
temperature, type of electrode or type/rating of gaskets used in the connection of
these valves etc.
c] Three copies of these lists shall be submitted
inbound form with two soft copies for use in future maintenance, repair,
replacement etc.
- Standardization of
Equipment:
a] As far as possible, the equipment shall be
standardized throughout the plant to facilitate maintenance, less spare
inventory requirements, ease in training etc. In particular, the following should
be standardized as a minimum:
i. HVAC equipment i.e. air handling units, fans,
heaters, ventilation units, autonomous units, etc.
ii. Valves: as far as possible, the approved
vendors shall be used for valves supply. In general, no more than five (5)
vendors shall be used for the plant.
iii. Pumps: as far as possible, shall be
standardized along with their components like mechanical seals, etc.
iv. Motors: as far as possible shall be
standardized.
v. Valve actuators: as far as possible, actuators
shall be standardized.
vi. Instruments: pressure, temperature & level
gauges, transmitters, flow indicators/ gauges and transmitters, switches,
totalizers, recorders etc. shall be standardized.
vii. Electrical relays, breakers, switchgear: as
far as possible shall be standardized.
viii. Use of gateways/interface with DCS shall be
minimized.
b] Departure from standardization is possible with
the approval of the Company/Engineer in special cases.
Adequate lighting shall be provided for all
indoor and outdoor equipment. All the
local instruments shall be readable at night. All the platforms stairs,
passageways shall have adequate lighting.
In general, no area of the plant has any
equipment, valve, instruments, etc. shall be under darkness during the night.
All the road crossings shall be provided with
lights.
The lux levels of different areas shall be as
specified or if not specified shall be as approved by the Company/Engineer.
Safety Provisions'
a] Provisions shall be made for safety during
operation and maintenance. Particular care shall be taken for the following:
i. All the platforms shall have railing with toe
plates.
ii. The roofs having any equipment, valves,
instruments or fittings shall have railing or parapet wall with stair(s) for
access.
iii. All the ladders, higher than 2.5 m shall be
provided with safety cages.
iv. All elevated equipment shall be provided with
platforms, railing, stairs or ladders (as approved for safe maintenance).
v. All openings such as ladders connection to
platforms shall be provided with removable barriers.
vi. Railings/walls, barriers etc. shall be provided around all the pits.
vii. Any other safety requirement not explicitly
specified in the specifications, but considered necessary by the
Company/Engineer shall be provided by the Contractor at no extra cost or time
consideration.
viii. Crossover platforms shall be provided over
pipes as per approval of the Company/Engineer.
The platform shall in general be provided to keep the shortest pedestrian route to and from any building or facility.
The Contractor shall develop and submit a detailed list of lubricants used for various equipment/parts of the plant.
The list shall include the name of the manufacturer
of the lubricant used, equivalent lubricant for each type used from other
manufacturers and:
i. Quantity of lubricants used per charge.
ii. Total quantity of each type of lubricant used
in order to assess the annual requirement.
iii. Time interval to replace the lubricant.
iv. Viscosity & other characteristics such as
viscosity index, flash point, pour point, etc.
Proper connection with valves and
pipings shall be provided at easily accessible locations for the collection of
samples. If required due to space
constraints, at the end of the sample collection, a hard pipe or a flexible pipe
shall be provided to make the collection of samples easier.
a] All protection relays shall be provided with
test sockets to enable secondary injection tests using a comprehensive test bench for the following equipment:
i. Generators,
ii. Medium Voltage equipment
iii. LV equipment
b] Similarly, the facilities shall be provided for
the injection of primary currents for all protection relays by use of primary
current injection test set.
c] All facilities shall be provided for safe
maintenance and, interalia, sufficient earthing switches having a padlock
facility or combined earthing breakers.
d] All microprocessor-based control &
monitoring systems and smart devices/instruments shall be fault-tolerant and
equipped with self-diagnostic facilities.
e] Test benches and kits shall be used for the
calibration and checks of the thermo-couples (other TCs than the one of the gas
turbines inlet temperature) and vibration pick-ups.