الشركة السعودية للكهرباء
الخدمات العامة / الأمن الصناعي
إدارة تطويرالامن
الصناعي
SAUDI ELECTRICITY COMPANY
SCOPE OF WORK AND TECHNICAL
SPECIFICATIONS
FOR INTEGRATED SECURITY SYSTEM FOR
TABLE OF CONTENTS |
|||||
|
|
||||
SECTION 1.0 |
INTRODUCTION |
|
|||
|
1.01 |
Project Scope |
|
||
|
1.02 |
Definitions |
|
||
|
|
|
|
||
SECTION 2.0 |
BASIC
REQUIREMENTS AND GUIDELINES |
|
|||
|
2.01 |
General Conditions
|
|
||
|
2.02 |
Kick-off Meeting
|
|
||
|
2.03 |
Base Design Phase |
|
||
|
2.04 |
Base Design Review |
|
||
|
2.05 |
As-Built Drawings
|
|
||
|
2.06 |
Progress Reporting |
|
||
|
2.07 |
Factory Test And Inspection |
|
||
|
2.08 |
Defects Discovered By The Company Before And After
Commissioning |
|
||
|
2.09 |
Maintenance/Operation Manual |
|
||
|
2.10 |
Test Record Book |
|
||
|
2.11 |
Loss Prevention Requirements |
|
||
|
2.12 |
Additional
HCIS Requirements for Aspiring Contractors (Bidders) |
|
||
|
|
|
|
||
SECTION
3.0 |
DESIGN
CRITERIA |
|
|||
|
3.01 |
General |
|
||
|
3.02 |
Environmental Conditions |
|
||
|
3.03 |
Applicable Codes and Standards |
|
||
|
|
|
|
||
SECTION 4.0 |
SYSTEM
DESIGN REQUIREMENTS |
|
|||
|
4.01 |
FENCE DETECTION SYSTEM |
|
||
|
4.02 |
Digital Closed Circuit Television (DCCTV) |
|
||
|
4.03 |
Access Control and Door Monitoring System |
|
||
|
4.04 |
Security Control Room |
|
||
|
4.05 |
ROAD RISING ARM BARRIERS |
|
||
|
4.06 |
UPS SYSTEM |
|
||
|
4.07 |
Employee Entry/Exit Shade |
|
||
|
4.08 |
Fire Alarm System |
|
||
|
4.09 |
Crash- Rated Main Plant Sliding Gate |
|
||
|
4,10 |
Crash-Rated hydraulic barrier at Main Plant Gate
|
|
||
SECTION 5.0 |
SCOPE OF
WORK |
|
|||
|
5.01 |
Project Description |
|
||
|
5.02 |
Summary of Work |
|
||
|
5.03 |
Related Work |
|
||
|
5.04 |
Electrical Works |
|
||
|
|
|
|
||
SECTION 6.0 |
SYSTEM
SPECIFICATION |
|
|||
|
6.01 |
General |
|
||
|
6.02 |
·
Fence Detection System
|
|
||
|
|
·
Vibration
Detection |
|
||
|
6.03 |
Digital Close Circuit Television Monitoring System
(DCCTV) |
|
||
|
6.04 |
Access
Control System |
|
||
|
6.05 |
Door monitoring system |
|
||
|
6.06 |
Road Arm Barriers |
|
||
|
6.07 |
Security Control Room Requirements |
|
||
|
6.08 |
Fire
alarm system |
|
||
|
6.09 |
Crash-
Rated Main Plant Sliding steel Gate |
|
||
|
6.10 |
Crash-Rated hydraulic barrier at Main
Plant Gate
|
|
||
|
6.11 |
UPS System
|
|
||
SECTION 7.0 |
TESTING AND
COMMISSIONING |
|
|||
|
7.01 |
Type Test Report |
|
||
|
7.02 |
Acceptance Test Plan and Procedures |
|
||
|
7.03 |
Pre-Commissioning Test – All Electronic Equipment
Cables |
|
||
|
7.04 |
Final Acceptance and Commissioning Tests |
|
||
|
7.05 |
Test Equipment
|
|
||
|
|
|
|||
SECTION 8.0 |
TRAINING
PROGRAM |
|
|||
|
|
|
|
||
SECTION 9.0 |
START-UP AND
OPERATION SPARE PARTS |
|
|||
|
9.01 |
START-UP AND OPERATION SPARE PARTS |
|
||
|
|
|
|
||
SECTION 10.0 |
MAINTENANCE
SERVICE |
|
|||
|
10.1 |
MAINTENANCE SERVICE |
|
||
|
10.2 |
PAYMENT |
|
||
|
|
|
|
||
SECTION 11.0 |
DRAWINGS AND
ATTACHMENTS |
|
|||
|
|
|
SECTION 1.0 INTRODUCTION
1.01 PROJECT
SCOPE
This specification established
the minimum requirements necessary for the design, installation, construction,
testing, commissioning, training, and maintenance of an Integrated Security
System for Saudi Electricity Company Power Plant. The types
of the system addressed by this specification include but are not limited to
the following:
1. FENCE
DETECTION SYSTEM
2. Digital
Closed Circuit Television (DCCTV).
3. Access
Control and Door Monitoring System.
4.
5. . road arm
barriers
6. Crash – rated
main plant sliding gate.
7. Crash-Rated hydraulic barrier at Main Plant
Gate.
8. fire
alarm .
9. Uninterruptible Power Supply (UPS)
System
10. Turnstiles
This specification shall be in
accordance to the standard outlined by the High Commission for Industrial
Security (HCIS), COMPANY specification for civil, electrical, and mechanical
work, engineering practices, safety, health, and environment.
The specification
will be based on the field proven latest technology available worldwide with
high qualities, in order to ensure the control of security process, which
COMPANY needs to counteract any possible danger at present or in the near
future.
1.02. DEFINITIONS
CONTRACTOR : CONTRACTOR
responsible for the engineering, supply, installation, testing/commissioning,
training and maintenance services for the Integrated Security System.
ISS : Integrated Security System, comprising of
a Detection System, Digital Closed
Circuit Television, and Access Control System.
HCIS : High Commission for Industrial Security
SSD : Security and Safety Directives
PTZ : Pan, Tilt, Zoom
DCCTV : Digital Closed Circuit Television
DVR : digital video recording (DVR)
CCD : Charge Coupled Device
TFT : Thin Film Transistor
LCD : Liquid Crystal Display
PIN : Personal Identification Numbers
FAT : Factory
Acceptance Test
COMPANY : Saudi
Electricity Company (SEC)
*** END OF SECTION 1.0 ***
SECTION 2.0 BASIC
REQUIREMENTS AND GUIDELINES
The
CONTRACTOR of the PROJECT shall observe the following:
2.01 GENERAL CONDITIONS
A. All components and accessories required
for the satisfactory operation of the WORK covered under the scope of this
PROJECT, either specified in detail or not, shall be supplied and installed by
the CONTRACTOR, as necessary.
B. The engineering design and specification
of equipment/materials supplied under this PROJECT shall be in accordance with
this Scope of Work and Technical Specifications and COMPANY Standards. However,
in case of a conflict with the requirements, the CONTRACTOR shall bring this to
the attention of the COMPANY and shall obtain COMPANY approval in writing for
any such applicable requirements of this PROJECT. The CONTRACTOR shall have no
right to decide on his own requirements in case of any such conflict and/or any
eventuality. They will be doing so at his own risk and cost while the COMPANY
reserves the right to reject any or complete part of such WORK carried out by
the Contractor's own decision.
C. The
drawings enclosed with this Scope of Work and Technical Specifications are only
conceptual for the information of the CONTRACTOR and are to be read in
conjunction with this Scope of Work and Technical Specifications. CONTRACTOR
shall develop detailed design drawings for construction based on these
conceptual drawings.
D. Copies
of existing drawings, utility drawings, design calculations, technical report
and other information as deemed appropriate by the COMPANY may be provided to
the CONTRACTOR upon request, if available. However, if such information is not
available, then the CONTRACTOR should be responsible for the independent development of the
information required to complete the PROJECT specified.
E. The
specification of equipment and materials specified herein are to be considered
as the minimum requirements, and the bidders shall carry out their basic and
detailed design necessary for the specific technical proposal. The entire
system shall be designed and executed in a very high standards and quality.
F. The
CONTRACTOR shall bring to the attention of the COMPANY, any erroneous, inferior
to HCIS standards, or outdated specification of equipments and materials specified
in this document during Bid Clarification Stage for immediate resolution and
inclusion of the appropriate changes and modifications as decided by the
COMPANY shall be part of the Contractor's Technical Proposal Package.
G. The
detailed design shall be finalized through design conference based on the
guideline drawings issued hereof, manufacturer’s drawings, and calculation data
sheets.
H. All
documents, drawings data and instruction books to be submitted by the
CONTRACTOR shall be written in English language and Metric Unit System.
I. All
nameplates to be incorporated in the WORK shall be permanently and legible
marked in English.
J.
All WORK including test
equipment services for the test and inspections required by the COMPANY shall
be furnished by the CONTRACTOR.
K.
ALL MENU AND ALERT
AND WINOWS ON MIONTOR SHALL BE IN ENGLISH AND ARBIC.
L COMPANY REPRESENTATIVE(S) shall be trained on the programming,
maintenance and operation of the Integrated System by the CONTRACTOR.
2.02 KICK-OFF MEETING
A kick-off meeting will be held
shortly after the contract has been awarded.
This meeting will finalize the Scope of Work and Schedule and will give
the CONTRACTOR an opportunity to ask questions related to carrying out his
responsibilities. It will also provide
the COMPANY, as well as the CONTRACTOR, an opportunity to clarify details.
2.03 BASE
DESIGN PHASE
2.03.1 The base design phase of the PROJECT is
a 6-8 week period of preliminary engineering.
The purpose of the PROJECT base design work is to completely define the
PROJECT in enough detail to satisfy the COMPANY so that all requirements of
planning, design, and operation are being incorporated. Information developed during the base design
shall be used as a guide throughout the PROJECT. Five (5) sets of preliminary design drawings
and information shall be submitted to the COMPANY four (4) weeks in advance to
review and offer comments at the Base Design Review Meeting.
2.03.2 The base design document shall comprise
as a minimum of the following:
a. Scope of Work
b. Design Basis (includes design
calculation)
c. Description of the PROJECT
d. PROJECT Detail Schedule and Critical
Path
e. Major Materials Purchase Requisitions
(Preliminary)
f. Following Design Drawings (will be
supplied by CONTRACTOR):
1. Security System Block Diagram
2. Security System Equipment Layout
3. Security System Wiring and Equipment
Interconnection Diagrams
4. Security Control Center Room and
Equipment Drawings
5. Camera Mounting
Pole .
6. Uninterruptible Power Supply Room and
Equipment Drawings
7.
8. Drawing
Control Sheet.
9. Employee
Access Shade.
.
g. Site Project Plan
h. QA/QC Plans for Procurement and
Construction
i. Job Safety Plan
j. Site Security Plan
2.03.3 The Scope of Work document consists of
multiple “A4” size type document containing a minimum of the following
information:
a. PROJECT Summary
b. Design Basis and Data
c. Description of Facilities
d. Testing and Commissioning Procedures
e. Maintenance Aspects
f. Special considerations including
design, construction/ operation constraints (if any), problem areas, and
proposed solutions.
g. PROJECT Schedule covering all phases
including construction and commissioning.
h. Job Order Number and Phase Listing
i. Itemized listing of all
equipment/facilities to be installed and description of all WORK to be
accomplished. This listing is to be
broken down by location, job phase, and quantities of like items.
2.04 BASE
DESIGN REVIEW
After
completing the base design, the CONTRACTOR shall present his base design for
technical review. In general, the
COMPANY shall require the CONTRACTOR to send the Contractor's Project Manager
and the Design/Construction Engineers to the COMPANY for the presentations.
2.05 AS-BUILT DRAWINGS
After
the successful completion of the PROJECT, certified as-built drawings of all
related WORK shall be submitted in the form of one (1) high quality
transparency (Mylar) and five (5) prints (Paper) and one (1) softcopy in CD.
2.06 PROGRESS REPORTING
2.06.1 The CONTRACTOR will submit Monthly
Progress Reports for the PROJECT to the responsible COMPANY
REPRESENTATIVE. For this purpose, the
total WORK shall be divided into:
a. Engineering and Design
b. Procurement/Manufacture/Fabrication
Inspection and Delivery of Materials/Equipment
c. Construction and Installation
d. Testing and Commissioning
2.06.2 The following information shall be
included in the Progress Reports:
a. Percent of WORK completed as compared
to the weighted schedule used to assess WORK progress.
b. Statement of items worked on and/or
completed during the period.
c. Statement of items to be worked on
and/or completed during the following period.
d. Problem areas, which can have an
adverse effect on the schedule.
2.06.3 Bi-Weekly Construction Progress Meeting
shall be conducted between the COMPANY and the CONTRACTOR during the
construction phase. Other coordination
and interface meetings will be conducted, as required. CONTRACTOR shall prepare the minutes of progress
meeting to be concurred by the COMPANY REPRESENTATIVE.
2.07 FACTORY
TEST AND INSPECTION
All
materials/equipment shall be subject to tests according to applied standards or
accepted practice, or as may be decided by the COMPANY REPRESENTATIVE.
2.07.1 The CONTRACTOR shall submit a detailed
testing program to the COMPANY REPRESENTATIVE for review at least two (2)
months before the commencement of factory tests.
2.07.2 Three (3) sets of Test Report shall be
submitted immediately to the COMPANY for evaluation. Three (3) sets of Test Report will be
submitted prior to material delivery.
Test Report should indicate whether the material/equipment tested,
passed, or failed the requirements.
2.08 DEFECTS DISCOVERED BY THE COMPANY
BEFORE AND AFTER COMMISSIONING
2.08.1 For any defects, which are detected or
discovered before the commissioning of the PROJECT, the CONTRACTOR shall be
informed through the COMPANY REPRESENTATIVE.
The CONTRACTOR shall take necessary corrective actions.
2.08.2 For any defects or malfunctions which
are detected or discovered within one calendar year after the commissioning of
the PROJECT, the COMPANY REPRESENTATIVE will make the necessary investigation
and:
a. If a component is found by the COMPANY
to be defective, the CONTRACTOR shall make arrangements to test, repair or
replace the component without cost to the COMPANY within two (2) weeks or
agreed period by the COMPANY from the time it is handed over to them through a
letter from the COMPANY.
b. If a defect is found in the design or
installation, the CONTRACTOR shall be informed through a letter. The CONTRACTOR shall take corrective actions
at his own cost within mutually agreed period.
c. If malfunction appears to be caused by
a defect in the materials supplied by the CONTRACTOR, but the defect cannot be
readily pinpointed by the COMPANY REPRESENTATIVE, the COMPANY shall contact the
CONTRACTOR in writing and provide the necessary shutdowns and work permit to
the CONTRACTOR REPRESENTATIVE who shall locate the faulty component and assist
in carrying out repairs, if required.
2.9 MAINTENANCE/OPERATION
MANUAL
This document will be prepared
at the end of the design stage. The book
will contain all basic drawings and CONTRACTOR equipment catalog and operation
information (in original, not Xerox copies/ (photocopies)) for the specific
equipment installed. Basic operating
system(s), procedure(s), service and maintenance instructions, and philosophy
will be described. All information which
may be required by the facility operator (documentation of the software
including the operating system) will be included as referenced including
factory test report. Total number of
sets required to be submitted to the COMPANY is seven (7).
2.10. TEST RECORD BOOK
The CONTRACTOR shall provide a
"Test Record Book" which shall include a complete and detailed record
of all tests conducted for material/ equipment, including factory source
materials and acceptance tests, field tests, start-up and acceptance tests
conducted for the entire PROJECT.
Three (3) copies of the
"Test Record Book" are to be submitted within thirty (30) days after
completion of the PROJECT.
2.11 LOSS PREVENTION REQUIREMENTS
The CONTRACTOR and its
SUBCONTRACTOR shall strictly comply with the following Loss Prevention
requirements, in addition to the stipulations in Schedule A - General Terms and
conditions of CONTRACT:
A. General Requirements
1. Strict adherence to all applicable
provisions of the Accident Prevention and Construction Safety Manuals. The CONTRACTOR
shall provide and use adequate warning signs, portable barricades, warning
lights and personal protective equipment at the JOB SITE.
2. The CONTRACTOR shall submit his Loss
Prevention Program to the COMPANY sufficiently in advance to obtain their approval
prior to commencement of WORK at site. The CONTRACTOR shall ensure that the
following requirements are incorporated in the submittal of the Loss Prevention
Program.
a. Cover
Page complete with references, as follows:
- Contractor's Name
- Title of Submittal
- PROJECT Title
- CONTRACT Number and Location
-
Company's Name
b. Table
of Contents.
c. Contractor's
COMPANY Safety Policy Statement complete with signature over printed name and
title of Contractor's Management REPRESENTATIVE.
d. Program
Contents applicable for implementation during the PROJECT execution.
e. Attachments
necessary to supplement the program.
- PROJECT Table of Organization
- Construction Schedule
- Plan
Layout for Temporary Facilities.
3. Provide necessary personal protective
clothing (i.e. head, eye, face, hand, and foot protection and respiratory
protective equipment) including personal protective equipment for fall
protection such as safety belts and lifelines, and implement wearing them.
4. Provide and use adequate and suitable
safety/warning signs, cordon tapes, portable barricades and warning lights to
protect the safety of COMPANY and
CONTRACTOR personnel and the public, and to prevent damage to property.
5. Provide first aid facilities and must
have certified employee to administer first aid and cardio-pulmonary
resuscitation.
6. Refrain from using mechanized
excavation equipment within restricted areas unless cleared and permitted to do
so.
7. Request in advance a clearance for
de-energizing the interfacing points and observe grounding procedures.
B. PROJECT Involving Erected Works
1. Submit his heavy equipment (i.e. cranes
and bucket trucks) to the COMPANY for safety inspection and certification and
correspondingly stuck with green safety sticker.
2. Furnish necessary ladders and platforms
(scaffolds). Ladders shall be of good and standard design, safety practices
shall be followed in positioning ladders. Scaffolds should be designed, built,
and inspected by a competent engineer.
C. Project Involving Welding and
Cutting Operations
1. Provide suitable fire extinguishers to
be used in case of fire emergencies.
2. Provide the welding gas cylinders with
suitable rack that is equipped with security chain(s).
D. Project Near Energized Lines or
Equipment
1. Observe working clearances when working
near energized line or equipment.
E. Project
Requiring the Use of Chemical(s)
1. Submit material safety data sheets
(MSDS) of chemicals required or which are to be used in the execution of the
PROJECT.
F. Storage of Materials
In order to
prevent theft/loss of material/equipment, the CONTRACTOR at site shall take all
necessary precautionary measures but not limited to:
1. All materials under this CONTRACT be
stored by CONTRACTOR in safe and
secured locations even if it is for short period of time.
2. If the equipment/materials are to be
retained in substations for a substantial period, then the CONTRACTOR shall
ensure that they are kept in locked containers or other
appropriate method of storage, which
will keep the materials/equipment not easily noticeable by people with any
intention of theft or pilferage. Moreover, such containers are to be placed at
a distance from the fence/boundary wall.
3. CONTRACTOR shall also consider other
factors (i.e. temperature, solar radiation, humidity) affecting storage of
materials and equipment being stored in containers to avoid any damage during
such storage period.
2.12 ADDITIONAL HCIS REQUIREMENTS FOR
ASPIRING CONTRACTORS (BIDDERS)
The aspiring
CONTRACTOR (Bidders) for this project shall comply with the following HCIS
requirements:
A. The aspiring CONTRACTOR for this project
shall be a Saudi Owned Company.
B. The aspiring CONTRACTOR shall submit a
comprehensive Company Profile consisting of complete information about Company
owner(s), experiences in Security System projects, and resume of all personnel
who will work in the project.
C. The aspiring CONTRACTOR shall possess a
valid license from the Ministry of Interior permitting them to execute projects
pertaining to Security System with valid commercial registration number
indicating the type of operation, which includes, import, design, install and
maintenance of Electronic Security Systems.
D. The aspiring CONTRACTOR shall have
qualified personnel to do the engineering, installation, maintenance and
support after sales works.
E. The aspiring CONTRACTOR shall submit a
written promissory guaranteeing of support after sales services, including
maintenance, replacement, and spare parts of the entire Security System during
the lifetime of the system.
F. The aspiring CONTRACTOR shall submit a
written promissory, considering all documentations and drawings pertaining to
the project as very highly confidential and shall not be distributed or shown
in part or in whole to any of its other clients or prospective clients.
*** END OF SECTION 2.0 ***
No comments:
Post a Comment