 SCHEDULE “C”                                                                 CONTRACT NO.

 

 

CONTRACT PRICE AND PAYMENT PROVISIONS

 

 

1.         CONTRACT PRICE

 

          As full and complete compensation for CONTRACTOR’s performance of the WORK and all of the CONTRACTOR’s obligations hereunder in accordance with the terms and conditions of this CONTRACT, COMPANY shall pay CONTRACTOR a CONTRACT Price consisting of:

 

          1.1     Labor Rates as specified in Pricing Attachment I.

 

          The rates set forth in Pricing Attachments I are not subject to escalation for any reason. No adjustments in compensation shall be made as a result of changes in the value of any currency.

 

2.         LABOR RATES

                  

          2.1     Monthly Labor Rates constitute all-inclusive payment to CONTRACTOR per month worked based on eight (8) hours per day and five (5) days per week. The Monthly Labor Rates shall only apply to actual man-months worked including COMPANY authorized travel time between the base WORK location as specified in the SERVICE ORDER and other WORK locations as may be required in the performance of the WORK. However, partial man-month worked shall be calculated in accordance with Paragraph 8.1 of this Schedule “C”.

 

          2.2     COMPANY shall compensate CONTRACTOR for overtime premium costs for any hours worked in excess of eight (8) hours per day and five (5) days per workweek or for hours worked on holidays and rest days in accordance with Paragraph 8.2 of this Schedule “C”. However, all overtime WORK shall be subject to COMPANY REPRESENTATIVE’S prior written approval.

 

                2.3     Monthly Labor Rates set forth in Pricing Attachment I of this Schedule “C” also includes:

 

                   2.3.1   Provision by CONTRACTOR at no additional cost to COMPANY for any necessary supporting staff (technical secretary, typist, translator, driver, etc.) as CONTRACTOR may require whose functions are not directly related to the performance of the WORK described in Schedule “B”.

 

          2.4     Monthly Labor Rates billings shall commence when the COMPANY REPRESENTATIVE certifies that CONTRACTOR’S personnel has commenced the WORK on specific SERVICE ORDER.

 

          2.5     The normal WORK week for CONTRACTOR’S personnel shall be consistent with the Labor and Workmen Law of the Kingdom of Saudi Arabia. CONTRACTOR’S actual WORK schedule, including overtime worked by CONTRACTOR personnel, shall be in accordance with the schedule authorized by COMPANY. The Monthly Labor Rates represent payment by COMPANY to CONTRACTOR, and not to CONTRACTOR’s personnel.

 

          2.6     Monthly Labor Rates include all costs such as camp, catering and transportation, SITE overheads, maintenance costs, all direct labor costs, Ramadan premiums, vacation pay, holiday pay, sixth/seventh-day pay, payroll insurance, taxes, fees of every kind and nature, insurances including Saudi  Arab  social  insurance,  sick pay, completion and retirement bonuses, travel  time to and from the WORKSITE, subsistence, living allowances, safety costs, small tools, consumables, and all burdens and overheads as well as profit.

 

3.         TIME REPORTING

           CONTRACTOR shall submit to COMPANY REPRESENTATIVE for his review duplicate copies of the following:

 

          3.1     A monthly detailed timesheets listing the categories and amounts of personnel for which compensation is requested for the previous scheduled month. 

 

          3.2     CONTRACTOR shall commence submission of such timesheets immediately upon commencement of the SERVICE ORDER and continue to submit them until their completion.

 

          3.3     COMPANY REPRESENTATIVE signature on the detailed timesheets shall only certify the time periods involved, and shall not constitute approval of any request for compensation.

 

4.         INVOICING AND PAYMENT

 

          4.1     On or before the tenth (10th) day of each Gregorian month during the performance of the WORK, CONTRACTOR shall invoice COMPANY for WORK performed during the preceding month and not included on previous invoices.

 

          4.2     Each monthly progress invoice shall be accompanied by copies of all SERVICE ORDERS and original timesheets of CONTRACTOR’s personnel certified by the COMPANY REPRESENTATIVE for the time period actually worked on specific SERVICE ORDER, and other supporting documents as may be required by COMPANY to substantiate the invoiced amount. However, the final invoice shall be accompanied by the original SERVICE ORDER and original supporting documents as required.

 

          4.3     CONTRACTOR shall submit invoices and supporting documentation in an original plus four (4) copies to:

 

                   The Controller, Controller’s Department

                   Central Operating Area

                          

          4.4     CONTRACTOR shall submit together with its progress/monthly invoices a written statement that CONTRACTOR has fully paid the salaries (including benefits/compensations, as applicable) of their personnel engaged in the WORK for the billing month. Failure by CONTRACTOR to submit the required statement may cause COMPANY to withhold any amount due  CONTRACTOR until such statement is submitted to the COMPANY and, if so directed by a competent Saudi Arab Government Authority, pay from such withheld amounts any CONTRACTOR’s personnel any amount that may be due from CONTRACTOR.

 

          4.5     All invoices and supporting documents shall be submitted on CONTRACTOR’S original letterhead, showing CONTRACTOR’S name, address, CR number, phone, and facsimile (fax) numbers, and with CONTRACTOR’S stamp affixed on it.

 

          4.6     After certification of each invoice by COMPANY REPRESENTATIVE, COMPANY shall promptly pay CONTRACTOR the sum due.

 

          4.7     All payments to CONTRACTOR shall be made by cheque at COMPANY’S Headquarters Office in Saudi Arabia or mailed to such address as CONTRACTOR requests in writing

         

          4.8     On the expiration date of this CONTRACT and after fulfillment by CONTRACTOR of all of its duties and obligations under this CONTRACT, CONTRACTOR shall submit to COMPANY its final invoice together with the following documents:

 

                   4.8.1   Proof satisfactory to COMPANY that all costs incurred by CONTRACTOR in the performance of the WORK have been satisfied and paid, that there are no unsatisfied claims or injuries to persons or property and that no other indebtedness exists in connection with the WORK for which CONTRACTOR is responsible (or if such claims or indebtedness exists, the in lieu of the foregoing, CONTRACTOR may provide COMPANY with appropriate information and consonants sufficient to indemnify and hold COMPANY harmless from any liability connected with said claims or indebtedness); and

 

                   4.8.2   Any and every document, receipt, statement of account, affidavit, or assurance which COMPANY required as necessary or appropriate to ensure immunity to COMPANY from any and all liens or claims for which COMPANY might be or become liable; and

 

                   4.8.3   Proof satisfactory to COMPANY that all COMPANY Identification Cards and/or Stickers furnished to CONTRACTOR under this CONTRACT has been returned to COMPANY’S Industrial Security Department; and

 

                   4.8.4   Releases to COMPANY from CONTRACTOR by execution of Final Receipt and Release Agreement (SEC Form # 15076) and from each assignee under this CONTRACT, discharging COMPANY from all liabilities, obligations and claims arising out of or under this CONTRACT, except for final payment.

 

          4.9     After COMPANY’S receipt of the foregoing documents and after all adjustments to CONTRACT Price and all unsettled matters under this CONTRACT have been disposed and after verification of CONTRACTOR’S final invoice, COMPANY shall pay CONTRACTOR all outstanding sums properly payable.

 

         4.10    Pursuant to Paragraph 22.2 of Schedule "A" of this CONTRACT, COMPANY will deduct an amount equal to (15%) from each and every Non-Resident CONTRACTOR's invoice.

 

5.         COMPANY’S AUDIT RIGHTS

 

          CONTRACTOR and it's affiliated companies shall maintain books, records, correspondence, instructions, plans, drawing, receipts, vouchers, memoranda, and other evidence (the foregoing constitute “records” for the purpose of this Paragraph), according to such accounting procedures and practices and practices as are satisfactory to COMPANY, sufficient to accurately and properly reflects costs incurred by CONTRACTOR and invoiced to COMPANY under this CONTRACT and the disposition of any materials, tools, or vehicle provided by COMPANY to CONTRACTOR. COMPANY, or any the firm of auditors appointed by COMPANY shall have access, at all reasonable times, to all such records for the purpose, of auditing and verifying costs or for any other reasonable purpose, and shall have the right to reproduce any such records. CONTRACTOR shall preserve and make available, and shall such records for a period of two (2) years after termination of this CONTRACT; provided, however, that if any such records are or may be required to resolve any claim pursuant to this CONTRACT, the period of retention, and the rights of access and examination described in this Paragraph shall continue until final disposition of such claim.

 

6.         SET-OFF

 

          COMPANY may deduct from amounts which are payable to CONTRACTOR under this CONTRACT any amounts which are payable to COMPANY by CONTRACTOR under this or any other CONTRACT between them.

 

7.         YEAR-END ACCRUED COST

 

          CONTRACTOR shall, on or before the 10th day of the beginning of each Hijra year during the progress of WORK, submit to COMPANY a detailed report for WORK completed during the previous Hijra year but not yet invoiced. The report shall include the description and quantity of WORK or percentage of WORK completed and the corresponding value.

 

8.         COMPENSATION FOR PARTIAL MAN-MONTH AND OVERTIME

 

For compensation to CONTRACTOR for Partial Man-Month and Overtime, the following formula shall apply:

         

          8.1     Partial Man-month

                    Compensation to CONTRACTOR for WORK performed for periods of less than a full month by any job classification and vehicle type shall be calculated as follows:

  

Daily Rate =

Monthly Rate x 12 Months

365 Days

 

Hourly Rate =

Daily Rate

8 Hours

         

                   8.2     Overtime

           Compensation to CONTRACTOR for the WORK performed in excess of the working hours specified in Paragraph 6.2 of Schedule “B” shall be calculated as follows:


Daily Overtime Rate =

Monthly Rate x 12 Months x 70%

365 Days

                                     

Hourly Overtime Rate =

Daily Rate x 70 %

8 Hours

 