POWER PLANT
PROJECT
POWER PLANT
SUPPLY & INSTALLATION OF NEW AIR CIRCUIT & COMPRESSORS
Introduction:
The service air circuit, which was established during the construction of the station in the early eighties, constituted an important basic tool - within the station's assistance package - in the completion of periodic and emergency maintenance work. Among the most important uses of the system were the following: Saving air at the time of unit maintenance for equipment that operates on air pressure, such as the Torque Wrench and Impact Wrench, which operate at a pressure of 100 psi.* Providing air for mechanical and electrical workshops.After the expansion of the station and the addition of 6 new turbines, the need for more service air appeared to meet the maintenance requirements, which prompted the addition of two new compressors.Now, after the old compressors have become obsolete and have frequent failures and their inability to meet the station’s need for service air, which causes delays in maintenance work, a project to supply and install heavy-duty air compressors (Heavy-Duty) has been approved, provided that this includes all accessories such as control and display panels, cooling Air, filters, tanks, pressure reducing platform, wiring and devices and all that the system requires to achieve the aforementioned requirements. And in the desire of the station to achieve higher returns from this system, the following requirements have been added Providing the appropriate amount of air to clean the air filters entering the turbine for 22 units, and cleaning the air filters for the turbine generator with six units (the new units), as the pulsing system was fed with service air after the compressors designated for the system failed at the time of the station’s construction. Providing air for the non-return valve test device, and the fuel injector test device at the mechanical maintenance workshop, where the workshop was supported with these two devices as part of the gas project Below, the general requirements, the technical requirements, as well as the cost schedule for the basic requirements are explained. Noting that the contractor is required to visit the station to get a better visualization of the system components and the proposed locations for the implementation of the compressor room and to see the old compressors to remove them as part of the project requirements, as well as to know the specifics of work in the station from safety procedures and others
To supply and install
heavy-duty air compressors including all accessories like control panels, air coolers, redundant
dryer, air vessels, pressure reduction skid, piping, and instrumentation, etc.
to meet the following requirements:
To
provide enough air for pulsing to clean inlet air filters for 22-GT MS7001E/EA
units and generator air filters for 6-GT MS7001EA units.
To
provide service air used for general maintenance: pneumatic tools like
impacting and torque wrench working at 100-psi.
To
provide air for the mechanical and electrical workshops.
General Technical Requirement:
The contractor shall deliver the compressors and their attachments and all that the project needs to the site of the seventh station.
The contractor must visit the station to inspect the site, take measurements, make the necessary studies, and attach them with the initial plans for all technical works (construction - mechanical - electrical) provided that they are handed over to the station for approval.
* The contractor must submit a plan for the training program necessary for two engineers and four technicians to be approved by the station. Note that the training will be on-site for operation and maintenance.
All technical works (structural - mechanical - electrical) are the responsibility of the contractor.
The construction works must comply with the degree of pressure bearing of the land on which the project is to be built, which will be submitted by the seventh station.
Installation of the equipment must be in accordance with the specifications and rules of the factory.
Before the initial receipt of the project, the performance of the system must be tested, with the need to clarify the method of testing within the offer.
The Contractor shall provide all necessary equipment for installation, inspection, and testing.
* The Contractor shall provide a guarantee of effective performance of the supplied equipment and devices.
* The contractor shall provide a list of all spare parts included in the project, as well as a list of spare parts proposed for supply by the contractor as a stock for two years after the end of the warranty period - as part of the project costs - for review and approval by the station before awarding.
* The contractor shall provide a workmanship guarantee and the necessary spare parts for a period of two years, starting from the date of issuance of the initial receipt certificate in accordance with the provisions of the company's general conditions. There will be a delay fine of 2/10000 of the contract value for each day in case the maintenance team is late to be present to solve the problem within three working days of notifying the plant to the contractor by fax. Note that the delay in solving the problem and restoring the system to its normal state after three working days from arriving at the site will be considered a delay. In the event of a malfunction that requires a longer work period, then the contractor must submit a work plan for the station explaining the reasons. In the event that spare parts are needed from the parts list for a period of two years in the station, the contractor must compensate them after using them in the least possible period.
The implementation period is 26 weeks from the date of handing over the worksite, which must take place within a week from the date of the baptism.
Any deficiency in this offering does not excuse the Contractor from providing the required service for the station in an integrated and approved system.
The conceptual layout plan for all the jobs is attached herewith.
The detailed outlines of the job will include but are not limited to the following:
Technical
Guidelines are enclosed to be considered where applicable.
Supply
of air compressors with all necessary accessories to the site.
The
contractor shall prepare his complete measurements, analysis, and proposed construction drawings for all
civil/mechanical/electrical works upon visiting the site and submit his
proposal approval.
Contractor
must provide a detailed outline of the training program for two engineers and
four technicians. Training will
be held on-site for both operation and maintenance.
All
civil/mechanical/electrical works will be the responsibility of the contractor.
Allowable
soil bearing pressure will be provided by CRB to be considered in the
construction.
Installation
of the equipment must be as per manufacturer specifications and
recommendations.
A
performance test must be done before handing in the provisional certificate. Documentation of the test procedure must be
included in the bid.
All
necessary materials and equipment needed for installation, commissioning and
testing are contractor responsibility.
The
contractor shall provide a performance guarantee for all machines and devices.
The
contractor shall provide a 2-year warranty, starting from the issuance of the
provisional acceptance certificate, of workmanship and spare parts against
supplied equipment and erection according -CRB general conditions.
All the spare parts list is to be included for review.
A list, recommended by contractor, of two years consumption spare parts
is to be submitted for approval and delivery upon acceptance as part of the
lumpsum.
Delivery
and total project period will be 26-weeks from the date of site delivery
certificate and it will be implemented one week after placement of the
purchase order.
Any
omission in this requirement SHALL NOT relief the bidder of his application to
deliver a system that is complete and will operate satisfactorily, reliably and
safely.
Main Technical Requirements:
Design Temp: The whole system is expected to run satisfactorily and safely at 55oC. Thus, all components of the design must meet this condition. Compressors cooling skid must be dependent on the number of compressors running and the required heat rejection rate to the cooling effluent.
The analysis must show the temperature upper and lower boundaries depending
on the allowable delivered air temperature and the material thermal shock
stresses.
Air
to be supplied from HEAVY-DUTY air compressors giving a total of…
Pressure: about 125-psi
Total Flow: about 2300-Cfm
Elec. Power: 460/3/60
Cooling:
by water,
cooled-down using chiller plant(s) for
all units
(redundant pumps &compressors).
No water-cooled by
fans.
Control Display: Digital; monitoring
information and alarms & protections and making operating adjustments.
V-type compressors are preferred. A substitute is negotiable.
Compressors
and chiller to share one digital control panel allowing for pressure-dependent
compressors sequence loading and alarm monitoring.
Compressors are to be enclosed in an isolated room. Air is to be blown inside the room (+ve pres.) through fine air filters.
The tentative location is near unit# 8, outside the turbine hall.
The contractor is to advise on the location during his visit to the plant.
Pressure drop and length of pipes
in addition to location constraints and obstacles that limit the location.
All
accessories such as valves, switches, and differentials, etc. are included.
Delivered
air from the compressors is to enter 3-large air storage tanks (around 12.5-m3
each) through a well-designed manifold to allow for elongated compressors
stand-by period.
Air
entering the manifold must be passed through an efficient air cooler and
redundant dryer.
Air
is to be stored @ around 125-psi. A
pressure reduction to 100-psi must occur before air exits the storage tanks and
enters the manifold leading to the mainline.
Hung pipes should lay adjacent to the existing one.
The contractor should give a provision for the interconnection with the old lines.
Connection with old pipes must be through isolation valves.
The contractor should advise on and include the points of isolation on the entire network to
ease the leakage inspection and hence maintenance.
Feed
line branching locations (a list of minimum acceptable sizes is included; the contractor is to submit a list with calculations):
Units
21/22 |
2” x 120m line from compressors room |
Turbine
Hall |
4” x 250m line from compressors room up to
each end of the turbine hall. |
Units’
Pulsing |
2” x 25m line for 22 units from nearest
point of 4” line to pulsing inlet air vessels. |
GT
17-22 Generators |
2” x 30m line from the nearest point of main the line to generator air filters pulsing system. |
Mechanical
Workshop & Check V/V Test Device |
2” x 90m line from the nearest point of 4” line
to workshop |
Electrical
Workshop |
2” x 75m line from the nearest point of 4” line
to workshop |
Compressed air must branch to the 22-gas turbines pulsing systems, new units generators’ air filters and to the maintenance outlets.
Locations are as follows:
|
|
Quantity |
Branch
Size (min.) |
|
|
|
Units |
1-outlet
each turbine side (44 sides) |
1 ½” x
5m |
|
|
|
Units’ Pulsing |
1-supply the line for each unit (22 units) |
2” x
25m |
|
|
|
Mechanical
Workshop |
4-outlets |
1 ½” x
5m |
|
|
|
Check V/V Test
Device |
2-supply
lines |
2” x
5m |
|
|
|
Electrical
Workshop |
2-outlets |
1 ½” x
5m |
|
|
|
Generators |
1-supply the line for each unit (6 units) |
2” x
30m |
|
|
Note:
all lengths listed are approximate. The contractor should make all necessary measurements on-site. |
|||||
The two existing compressors must be connected to the new network. The three old compressors must be removed as part of the project.
Pulsing system
compressors for inlet air filters must be removed.
Each
of the outlets and pulsing lines will have a pressure gauge and a shut-off valve. Outlets are all ¾” in size.
PRICE SCHEDULE
Item |
Work Description
Material(CIF) |
Construction & Erection |
Total (SR) |
||
1 |
All civil
works like a forced ventilated room with inlet air filters, foundations, etc. |
|
|
|
2 |
5 no. of air
compressors to provide the flow rate as per technical guidelines. |
|
|
|
3 |
Supply and
installation of pipes and piping components. |
|
|
|
4 |
Control
panel |
|
|
|
5 |
Chillers
|
|
|
|
6 |
3 no. air
storage vessels with dryers, instrumentation, and protection. |
|
|
|
7 |
Two years spare parts list |
|
|
|
8 |
|
|
|
|
9 |
|
|
|
|
10 |
|
|
|
|
Required manuals and drawings in addition to on-site
training is part of the lumpsum price.
PRICE SCHEDULE
Item |
Work Description
|
Material(CIF) |
Erection |
Total |
1 |
All civil
works like a forced ventilated room with inlet air filters, foundations, etc. |
The Total Estimate is Given as a Reference. These Two Fields are to be Filled by
Bidders. Documentations and Drawings and on-site training are Included for each item in its total cost. |
240,000 |
|
2 |
5 no. of air
compressors to provide the flow rate as per technical guidelines. |
950,000 |
||
3 |
Supply and
installation of pipes and piping components. |
180,000 |
||
4 |
Control
panel |
85,000 |
||
5 |
Chillers
|
190,000 |
||
6 |
3 no. air
storage vessels with dryers, instrumentation, and protection. |
175,000 |
||
7 |
Two years spare parts list |
180,000 |
No comments:
Post a Comment