REFERENCE GUIDELINES FOR CALCULATING - consulting

Breaking

Breaking News

Wednesday, 11 August 2021

REFERENCE GUIDELINES FOR CALCULATING

 



REFERENCE GUIDELINES FOR CALCULATING

 

PERFORMANCE INDEXES

&

DATA REPORTING INSTRUCTIONS

 

 TABLE OF CONTENTS

 

·        DEFINITIONS

 1.      Outages

2.    De-ratings

3.      Reserve Shutdown - RS

4.      Non-Curtailing Event – NC

5.    Event Transitions

6.    Unit Generation performance 

 

·        TIME PERIOD CALCULATIONS FOR OUTAGES & CAPACITY DERATING

  ·        PERFORMANCE INDEXES AND EQUATIONS

  INSTRUCTIONS FOR GENERATING UNIT EVENT REPORTING

  

·        DEFINITIONS

 

1. Outages

An outage exists whenever a unit is not synchronized to the grid system and not in a Reserve Shutdown state.

An outage starts when the unit is either desynchronized from the grid or when it moves from one unit state to another .The outage ends when the unit is synchronized to the grid or moves to another unit state whose allowed transfer applicability is shown in table no1.

 

In the case of moving from one unit state to another, the exact date and time that one outage ends will be the same as the next outage starts. Whenever two statuses overlap, for example, forced outage (U1) & planed outage (PO) the maximum time period counted for (U1) 168 hours or less, till the unit, enters in (PO) state. in case (U1) happens and (PO) dose does not appear within the maximum allowed period of 168 hours unit state will enter maintenance outage (MO) until unit receives a(PO).

It is agreed that, in case A unit is forced outage(U1) , before the commencement of planned outage (PO) , which is just due to commence by a period shorter than, one day, the time period in question will be counted as (PO).          

 

The general outage event classification is divided into seven distinct event types.

 

PO   -     Planned Outage

An outage that is scheduled well in advance and is of a predetermined duration, lasts for several weeks and occurs only once or twice a year. 

  It is agreed that a planned outage can be all types of scheduled maintenance such as all inspection (major and minor), including repair job & permanent modification normally planed during annual maintenance programs.

 

MO  - Maintenance Outage

An outage that can be deferred beyond the end of the next weekend, but requires that the unit be removed from service, another outage state, or Reserve Shutdown state before the next Planned Outage (PO). Characteristically, a MO can occur any time during the year, has a flexible start date, may or may not have a predetermined duration, and is usually much shorter than a PO.

 

SE   -     Scheduled Outage Extension

 scheduled outage extension is an extension of a Planned Outage (PO) or a

Maintenance Outage (MO) beyond its estimated completion date.

scheduled outage extension (SE) can take place when extra time is required to complete the essential  scope of work .

If any unexpected jobs come to surface during scheduled outage (MO ,PO) , then record the unit state as  forced outage(U1) and its maximum limit (168)hours .

Start of  (SE) and (U1) must be recorded precisely  mentioning month/ day / hour /minute from the termination of MO,PO.

   

SF   -   Startup Failure

An outage that results when a unit is unable to synchronize within a specified startup time following an outage or Reserve Shutdown.

 SF begins when the problem preventing the unit from synchronizing occurs. The SF ends when the unit is synchronized, another SF occurs, or the unit enters another permissible state.

 

Note :

The startup period for each unit is determined by the operating utility. It is unique for each unit, and depends on the condition of the unit at the time of startup (hot, cold, standby, etc.). A startup period begins with the command to start and ends when the unit is synchronized

 

U1    -    Unplanned (Forced) Outage — Immediate

An outage that requires immediate removal of a unit from service, another Outage State, or a Reserve Shutdown state. This type of outage usually results from immediate mechanical/electrical/hydraulic control systems trips and operator-initiated trips in response to unit alarms.

 

  It is agreed that (U1) will be allocated for a unit requiring immediate removal from service or the  following unit states : (PO, MO, SE,SF U1 ,U2, U3 & RS).

 

U2     -   Unplanned (Forced) Outage — Delayed

An outage that does not require immediate removal of a unit from the in-service state but requires removal within six hours. This type of outage can only occur while the unit is in service.

 

U3    -   Unplanned (Forced) Outage — Postponed

 An outage that can be postponed beyond six hours but requires that a unit be    removed from the in-service state before the end of the next weekend. This type of outage can only occur while the unit is in service.

 

   Notes on Reporting Outages

Typically following outages, equipment that was repaired or replaced is tested. These testing periods must be reported. The reporting procedure to follow depends on whether or not the unit was synchronized during the testing period:

 

a.   On-line testing (synchronized)

 

If the unit must be on line and in service at some reduced load to perform testing following a Planned Outage (PO), Maintenance Outage (MO), or Unplanned (Forced) Outage (U1, U2, U3, SF), report the testing as a Planned Derating (PD), Maintenance Derating (D4), or Unplanned (Forced) Derating (D1), respectively. The PD, D4, or D1 starts when the testing begins, and ends when testing is completed. Report any generation produced while the unit was on line during the testing period on the Performance Report.

 

b.  Off-line testing (not synchronized)

 

In cases where the unit does not have to be synchronized after the outage to perform testing, you can report the testing as part of the outage event .     

 The outage ends when the testing is completed and the unit is placed in service or enters another state.

 

 

 

2. Deratings

 A derating exists whenever a unit is limited to some power level less than the unit’s Net Maximum Capacity.

 A derating starts when the unit is not capable of reaching (100%) capacity. The available capacity is based on the output of the unit and not on dispatch requirements. The derating ends when the equipment that caused the derating is returned to service.

 

Report all deratings that are greater than (2%) of the unit’s Net Maximum Capacity and longer than 30 minutes in duration. Do not report deratings caused by ambient-related conditions or system dispatch requirements.

It is agreed that deratings must be calculated & reported if it is greater than (8%) of the unit’s Net Maximum Capacity and longer than (30 minutes) in duration where as gas turbine is being operated on crude oil .

 

 

 Derating events are  classified into 6 distinct types as follows:

 

PD  -     Planned Derating

A derating that is scheduled well in advance and is of a predetermined duration or to perform testing following a Planned Outage (PO).

 

      D4   -      Maintenance Derating

A derating that can be deferred beyond the end of the next weekend but requires a reduction in capacity before the next Planned Outage (PO) or to perform testing within a maintenance outage (MO). A D4 can have a flexible start date and may or may not have a predetermined duration.

 

DE  -     Derating Extension

An extension of a Planned Derating (PD) or a Maintenance Derating (D4) beyond its estimated completion date.

 

Use a DE only in instances where the original scope of work requires more time to complete than originally scheduled. If unexpected problems, or delays outside the scope of work are encountered which render the unit incapable of full load beyond the estimated end date of the PD or D4 , allocate D1 instead of DE . The DE must start at the same time

(month/day/hour/minute) that the PD or D4 ended.

 

D1   -     Unplanned (Forced) Derating — Immediate

A derating that requires an immediate reduction in capacity.

 

D2   -     Unplanned (Forced) Derating — Delayed

A derating that does not require an immediate reduction in capacity but requires a reduction within six hours.

 

D3   -     Unplanned (Forced) Derating — Postponed

A derating that can be postponed beyond six hours but requires a reduction in capacity before the end of the next weekend.

 

            Notes on Reporting Deratings

 

      Ambient-related Losses


Do not report ambient-related losses,. There are two reasons for this.

 First, the level of record keeping required to track these types of losses as events is excessive.

 Second, ambient-related losses are easily computed using  the Performance formula for energy generated losse; and that is simply multiply the difference between  Maximum Capacity  and Dependable Capacity by total number of  hours during the period under  study.

 

      System Dispatch Requirements

Sometimes units operate at less than full capacity for reasons other than ambient-related conditions or any auxiliary  equipment failures. This operating mode ,which is imposed by system dispatch requirements , is referred to as “Load Following”.

-          Load Following not reported as a de-rating event.

-          But incase any maintenance work or testing is carried out under the certain conditions during the Loading Following period, the work or testing should be recorded as Non-Curtailing(NC) event as explained latter .

 

 Ramping Up at Unit Startup and Down at Unit Shutdown

 

Each unit has a “standard” or “normal time for reaching full load capabilities after a full outage or ramping down (coming off line) to a full outage state. the operators know the units and can judge if a unit is taking longer than normal to ramp up after an outage or coast down for removal from service.

 

If a unit ramps up to the full load level OR up to the level of required load within the “normal” time period — set by the operators of the unit — following a full outage, there is no derating on the unit from the time of synchronization to the load point.

 

If the unit takes longer than normal ramp up time to the full load level OR up to the required load, then there is a derating. The generating capacity of the unit at the end of the normal period will be the level of the derate and the derate will last until the unit can either reach full load capability or level of required load.

 

There is no derating for unit shutdown. Each unit must be shutdown safely, with damaging equipment or posing a safety hazard to personnel. Some shutdowns are quick as in a unit trip; others are slower such as coast down to unit planned outages. In either case, the unit is not derated.

 

3.  Reserve Shutdown - RS

 

An event that exists whenever a unit is available for load but is not synchronized due to lack of demand. This type of event is sometimes referred to as an economy outage or economy shutdown.

 If a unit is shut down due to any equipment-related problems, whether or not the unit was needed by the system, report an Unplanned (Forced) Outage, Maintenance Outage, or Planned Outage, not a Reserve Shutdown.

 

While a unit is on RS, maintenance work is often performed that would have resulted in a unit outage or de rating had the unit been on line. This work can be reported as part of the RS event if, at anytime, the work can be stopped or completed without preventing the unit from:

 

a)   synchronizing after a normal startup cycle; and,

 

b)   reaching its available capacity after a normal loading cycle.

 

This criterion remains the same whether or not the unit was needed by the system.

 

 If maintenance work cannot be stopped or completed the Reserve Shutdown condition of the unit is altered and an outage or derating must be reported. If the unit cannot be synchronized while the work is being performed, an outage exists and the RS must end. If the unit cannot reach at  its available capacity while the work is being performed, a derating exists. The RS event does not end, but report the derating too. Estimate the available capacity as a result of the derating.

 

 

4.  Noncurtailing Event - NC

 An event that exists whenever equipment or a major component is removed from service for maintenance, testing, or other purposes that does not result in a unit outage or derating.

  An NC also can exist when a generating unit is operating at less than full capacity due to system dispatch requirements. During this period, equipment can be removed from service for maintenance, testing, or other reasons and be reported as an NC if both the following conditions are met:

 a)   The available capacity of the unit is not reduced below that required by system dispatch;

and,

 b)   Maintenance work can be stopped or completed and the units reach its net dependable capacity (NDC) level within its normal ramp-up time, if and when the unit was needed by the system.

 If the above conditions (a,b) cannot be met, report an outage or derating event rather than an NC.

  

 

5. Event Transitions

Sometimes events occur in succession with no intervening unit synchronization. These events are considered “related,” even though they must be reported separately. The matrix below describes the relationships between events and details permissible event type changes.

 

Allowable Event Type Changes

 

FROM

U1

U2

U3

SF

MO

PO

SE

RS

DE

U1- Immediate

Yes

No

No

Yes

Yes

Yes

No

Yes

 

U2- Delayed

Yes

No

No

Yes

Yes

Yes

No

Yes

U3 – Postponed

Yes

No

No

Yes

Yes

Yes

No

Yes

SF – Startup Failure

Yes

No

No

Yes

Yes

Yes

No

Yes

MO - Maintenance

Yes

No

No

Yes

Yes

Yes

Yes

Yes

PO - Planned

Yes

No

No

Yes

No

Yes

Yes

Yes

SE – Extension

Yes

No

No

Yes

No

No

Yes

Yes

RS–Reserve Shutdown

Yes

No

No

Yes

Yes

Yes

No

Yes

D1- Immediate

 

No

D2- Delayed

No

D3 – Postponed

No

D4 - Maintenance

Yes

PD - Planned

Yes

DE – Extension

Yes

 

“YES” denotes that a change from one event type to another without intervening synchronization is permissible and the end date of the first event can be the same as the start date of the successive event.

 “NO” indicates that there is no relationship between the event types and individual events separated by some period of time must be reported.

 

When there is no intervening synchronization between events, the start time of one event is the same as the end time of the immediately preceding event.

 

6.  UNIT GENERATION PERFORMANCE

 

Gross Maximum Capacity (GMC) 


It is the maximum capacity the unit can sustain over a specified period of time when not restricted by ambient conditions or deratings.

The GMC of a unit should change only as a result of a new performance test or permanent unit modification. GMC is never changed due to equipment problems, even if some of them persist for a lengthy period of time unless permanent modification is carried out.

 

It is agreed that gross maximum capacity (GMC) will be that capacity of a unit as prescribed by (International Standard Organization ISO) at 15 C, at sea level and relative humidity at 60%.

 

Gross Dependable Capacity (GDC) 

It is the gross power level that the unit can sustain during a given period if there are no restrictions

on equipment for its operation,  or regulatory restrictions.

 By definition, therefore, the GDC is the GMC modified for ambient limitations.

 

Gross Actual Generation (GAG)

 

GAG is the actual number of gross electrical megawatthours (MWh) generated by the unit during a given  period.

 

Gross available capacity (GAC)


GAC is the greatest capacity at which the unit can operate during the period of restriction caused by the derating.

 

Total Actual Capacity  (TAC)

TAC is the maximum total capacity for a generating unit, calculated at 50 C compressor inlet air temperature .

“It is agreed that Total Actual Capacity calculations will be carried out at 50 C Ambient”.

 

Net Maximum Capacity (NMC)  


NMC is the unit’s GMC, less any capacity (MW) utilized for that unit’s station service or auxiliary load.

 Net Dependable Capacity (NDC) 

NDC is the unit’s GDC, less any capacity (MW) utilized for that unit’s station service or auxiliary loads.

 

Net Actual Generation (NAG) 

NAG is the unit’s Gross Actual Generation (GAG) less any generation (MWH) utilized for that unit’s station service or auxiliary loads.

 

Net Available Capacity (NAC)

 NAC is the Gross available capacity)  GAC( less any capacity utilized for station service or auxiliary loads.

 

 ·        Calculations of outage time de-rating capacity  

 

 Service Hours  ) SH )

Sum of all Unit Service Hours.

 

Available Hours  ( AH )


sum of the Unit Service Hours (SH), Reserve Shutdown Hours(RS), Pumping Hours (if applicable), and Synchronous Condensing Hours (if applicable).

 

AH= SH+RSH+(PUMPING HOUR ) +( SYNCRONOUS  CONDENSING)

 

NOTE : PUMPING HOUR ARE ONLY APLICABEL FOR HYDRO ELICTRIC POWER UNIT .

 

Planned Outage Hours ( POH )


Sum of all hours experienced during Planned Outages (PO) + Scheduled Outage Extensions

(SE) of any Planned Outages (PO).

 

POH= PO + (SE of PO)

 

 

Unplanned Outage Hours ( UOH )


Sum of all hours experienced during  Unplanned (Forced) Outages (U1, U2, U3) + Startup Failures (SF) + Maintenance Outages (MO) + Scheduled Outage Extensions (SE) of any Maintenance Outages (MO).

 

UOH = (U1+U2+U3) + SF + MO + ( SE of MO)

 

Unplanned (Forced) Outage Hours ( FOH )

Sum of all hours experienced during Unplanned (Forced) Outages (U1, U2, U3) +

Startup Failures (SF).

FOH=  (U1+U2+U3) + SF

 

Maintenance Outage Hours  ( MOH )

Sum of all hours experienced during Maintenance Outages (MO) + Scheduled Outage Extensions (SE) of any Maintenance Outages(MO).

MOH = MO + ( SE of MO)

 

Unavailable Hours  (UH)

Sum of all Planned Outage Hours (POH) + Unplanned (Forced) Outage Hours (FOH) + Maintenance Outage Hours (MOH).

UH = POH + FOH + MOH

 

Scheduled Outage Hours – SOH

Sum of all hours experienced during Planned Outages (PO) + Maintenance Outages (MO) +Scheduled Outage Extensions (SE) of any Maintenance Outages (MO) and Planned Outages (PO).

 

SOH = PO+ (SE of PO) + MO + (SE of MO)

 

Period Hours  (PH)

 

Number of hours in the period being reported that the unit was in the active state.

 

Equivalent Seasonal Derated Hours - ESEDH

 

Net Maximum Capacity (NMC) - Net  Dependable Capacity (NDC) x Available Hours (AH) / Net Maximum Capacity (NMC).

 

(NMC --- NDC) x AH

                NMC

 

          Equivalent Unplanned  (Forced) Derated Hours – EFDH (D1, D2, D3)

 Each individual Unplanned (Forced) Derating (D1, D2, D3) is transformed into equivalent full outage hour(s).  This is calculated by multiplying the actual duration of the derating (hours) by the size of the reduction (MW) and dividing by the Net Maximum Capacity (NMC). These equivalent hour(s) are then summed.

 

  

Derating Hours x Size of Reduction*

                                                                              NMC

 

 NOTE: Includes Unplanned (Forced) Deratings (D1, D2, D3) during Reserve Shutdowns (RS).

 

Equivalent Planned Derated Hours – EPDH (PD, DE)

 

 

Each individual Planned Derating (PD,DE) is transformed into equivalent full outage hour(s). This is calculated by multiplying the actual duration of the derating (hours) by the size of reduction (MW) and dividing by the Net Maximum Capacity (NMC).  These equivalent hour(s) are then summed.

 

 

      Derating Hours x Size of Reduction*

                              NMC

 

 

NOTE: Includes Planned Deratings (PD) during Reserve Shutdowns (RS)..

 

Equivalent Unplanned Derated Hours – EUDH (D1, D2, D3, D4, DE)

      

Each individual Unplanned Derating(D1, D2, D3, D4, DE) is transformed into equivalent full outage hour(s).  This is calculated by multiplying the actual duration of the derating (hours) by the size of reduction(MW) and dividing by the Net Maximum Capacity (NMC). These equivalent hour(s) are then summed.

 

 

Derating Hours x Size of Reduction*

NMC

 

NOTE:Incudes Unplanned Deratings (D1, D2, D3, D4, DE) during Reserve Shutdowns (RS).

 

 

Equivalent Unplanned (Forced) Derated Hours During Reserve Shutdowns – EFDHR (D1, D2, D3)

 

Each individual Unplanned (Forced) Derating (D1, D2, D3) or the portion of any Unplanned (Forced) derating which occurred during a Reserve Shutdown (RS) is transformed into equivalent full outage hour(s).  This is calculated by multiplying the actual duration of the derating (hours) by the size of the reduction (MW) and dividing by the Net Maximum Capacity (NMC).

 These equivalent hour(s) are then summed.

 

 

Derating Hours x Size of Reduction*

NMC

 

          *    Size of Reduction is determined by subtracting the Net Available Capacity (NAC)  from the Net Dependable Capacity (NDC).  In cases of multiple deratings, the Size of Reduction of each derating will be determined by the difference in the Net Available Capacity of the unit prior to the derating and the reported Net Available Capacity as a result of the derating

 

 

Number of Planned Outages (PO) which occur from in-service state only

 

A count of the number of all Planned Outages (PO) reported on Event Report

 

(Since Scheduled Outage Extensions (SE) of Planned Outages are considered part of the original Planned Outage (PO), they are not included in this count.)

 

 

Number of Unplanned Outages(MO, U1, U2, U3) which occur from in-service state only

 

A count of the number of all Unplanned Outages (U1, U2, U3, MO) reported in the Event Report

does not include Startup Failures (SF) in this count.)

 

 

Number of Unplanned (Forced) Outages (U1, U2, U3), which occur from in-service state only

 

A count of the number of all Unplanned (Forced) Outages (U1, U2, U3) reported on the  Event Report do not include Startup Failures (SF) in this count.

 

Number of Maintenance Outages (MO), which occur from in-service state only

 

A count of the number of all Maintenance Outages (MO) reported on the Event Report

(Since Scheduled Outage Extensions (SE) of Maintenance Outages are considered part of the original Maintenance Outage (MO), they are not included in this count.)

 

·        PERFORMANCE INDEXES AND EQUATIONS

 

1.          Planned Outage Factor – POF

The formula for calculation is, as follows:

 

POF

=

Planned Outage Hours

X

100

Period Hours

 

 

2.          Unplanned Outage Factor – UOF

The formula for calculation is, as follows:

 

UOF

=

Unplanned Outage Hours

X

100

Period Hours

 

 

3.          Forced Outage Factor - FOF

The formula for calculation is, as follows:

 

 


FOF

=

Unplanned (Forced) Outage Hours

X

100

Period Hours

 

 

4.          Maintenance Outage Factor – MOF

The formula for calculation is, as follows:

 

MOF

=

Maintenance Outage Hours

X

100

Period Hours

 

 

5.          Scheduled Outage Factor – SOF

The formula for calculation is, as follows:

 

SOF

=

Scheduled Outage Hours

X

100

Period Hours

 

       6.          Unavailability Factor – UF

The formula for calculation is, as follows:

 

UF

=

Unavailable Hours

X

100

Period Hours

 

 7.           Availability Factor - AF

 The formula for calculation is, as follows:

 

AF

=

Available Hours

X

100

Period Hours


 

8.            Service Factor - SF

 The formula for calculation is, as follows:

 

SF

=

Service Hours

X

100

Period Hours

 


9.                   Seasonal Derating Factor – SEDF

 The formula for calculation is, as follows:

 

SEDF

=

Equivalent Seasonal Derated Hours

X

100

Period Hours

 

       10.            Unit Derating Factor - UDF

   The formula for calculation is, as follows:

                      

UDF

=

Equivalent Planned Derated Hours + Equivalent Unplanned Derated Hours

X

100

Period Hours


 

11.       Equivalent Unavailability Factor - EUF

The formula for calculation is, as follows:

 

EUF

=

Planned outage hours+ Unplanned outage hours +Equivalent Planned Derated Hours + Equivalent Unplanned Derated Hours

X

100

Period Hours


12.       Equivalent Availability Factor - EAF

The formula for calculation is, as follows:

 

EAF

=

Available hours - Equivalent Planned Derated Hours- Equivalent Unplanned Derated Hours - Equivalent Seasonal Derated Hours

X

100

Period Hours


 

13.       Gross Capacity Factor - GCF

The formula for calculation is, as follows:

 

GCF

=

Gross actual generation

X

100

Period Hours x gross maximum capacity

 

 14.       Net Capacity Factor - NCF

The formula for calculation is, as follows:

 

NCF

=

Net actual generation

X

100

Period Hours x Net maximum capacity

 

Note:  Net capacity factor calculated using this equation can be negative during a period when the unit is shutdown.

 

 15.       Gross Output Factor - GOF

The formula for calculation is, as follows:

 

GOF

=

Gross actual generation

X

100

Service Hours x gross maximum capacity

 

 16.       Net Output Factor - NOF

The formula for calculation is, as follows:

 

NOF

=

Net actual generation

X

100

Service Hours x Net maximum capacity


 

17.       Forced Outage Rate - FOR

The formula for calculation is, as follows:

 

FOR

=

Unplanned (Forced) Outage Hours

X

100

Unplanned (Forced) Outage Hours + Service Hours

 

 

18.       Equivalent Forced Outage Rate – EFOR

The formula for calculation is, as follows:

 

EFOR

=

Unplanned (Forced) Outage Hours + Equivalent Unplanned (Forced) Derated Hours

X

100

Unplanned (Forced) Outage Hours + Service Hours+ Equivalent un planed (Forced) Derated Hours during

Reserve Shutdowns (RS) Only

 

 

19.       Average Run Time - ART

The formula for calculation is, as follows:

 

ART

=

Service Hours

X

100

Actual Unit Start

 

 

20.              Starting Reliability – SR

The formula for calculation is, as follows:

 

SR

=

Actual Unit Start

X

100

Attempted Unit Start

 

  

Mean Service Time to Outage:

 

21a.     Mean Service Time to Planned Outage - MSTPO

The formula for calculation is, as follows:

 

MSTPO

=

Service Hours

X

100

Number of Planned Outages

(which occur from in-service state only)

 

 21b.     Mean Service Time to Unplanned Outage - MSTUO

The formula for calculation is, as follows:

 

MSTUO

=

Service Hours

X

100

Number of Unplanned Outages

(which occur from in-service state only)

 

                                        

21c.     Mean Service Time to Forced Outage - MSTFO

The formula for calculation is, as follows:

 

MSTFO

=

Service Hours

X

100

Number of Unplanned Forced Outages

(which occur from in-service state only)

 

 

21d.     Mean Service Time to Maintenance Outage - MSTMO

The formula for calculation is, as follows:

 

MSTMO

=

Service Hours

X

100

Number of  Maintenance Outages

(which occur from in-service state only)

 

 

Mean Outage Duration:

 

22a.     Mean Planned Outage Duration - MPOD

The formula for calculation is, as follows:

 

MPOD

=

Planned Outage Hours

X

100

Number of Planned Outages

(which occur from in-service state only)


22b.     Mean Unplanned Outage Duration - MUOD

The formula for calculation is, as follows:

  

MUOD

=

Unplanned Outage Hours

X

100

Number of Unplanned Outages

(which occur from in-service state only)

 

 

22c.     Mean Forced Outage Duration – MFOD

The formula for calculation is, as follows:

 

 

 

MFOD

=

Unplanned Forced Outage Hours

X

100

Number of Unplanned Forced Outages

(which occur from in-service state only)

 

 

22d.     Mean Maintenance Outage Duration - MMOD

The formula for calculation is, as follows:

 

MMOD

=

Maintenance Outage Hours

X

100

Number of Maintenance Outages

(which occur from in-service state only)

 

INDEXES FOR OPERATION PLAN


·        INDEXES FOR OPERATION PLAN

  

1- Availability Factor - AF

 This must be calculated on quarterly basis during a year. It is needed to be calculated for Steam, gas, combined cycle, diesel engine, generated unit as per following formula;

 

AF, Weighted @ NMC

=

Available Hours

X

100

Period Hours

 

 

2- Forced Outage Factor - FOF

 

This must be calculated on quarterly basis during a year. It is needed to be calculated for Steam ,gas, combined cycle, diesel engine, generated unit as per following formula;

 

FOF, Weighted @ NMC

=

Unplanned Forced Outage Hours

X

100

Period Hours

 

3- Maintenance Outage Factor – MOF

 

This must be calculated on quarterly basis during a year. It is needed to be calculated for Steam ,gas, combined cycle, diesel engine, generated unit as per following formula;

 

MOF Weighted @ NMC

=

Maintenance Outage Hours

X

100

Period Hours

 

 

4- Planned Outage Factor – POF

 

This must be calculated on quarterly basis during a year. It is needed to be calculated for Steam ,gas, combined cycle, diesel engine, generated unit as per following formula;

 

POF Weighted @ NMC

=

Planed Outage Hours

X

100

Period Hours

 

5- Gross capacity Factor -GCF

 

This must be calculated on quarterly basis during a year. It is needed to be calculated for Steam , gas, combined cycle, diesel engine, generated unit as per following formula;

 

GCF

=

Gross Actual Generation

X

100

Period Hours x Gross Maximum Capacity

 

 

6- Gross Output Factor - GOF

 

This must be calculated on quarterly basis during a year. It is needed to be calculated for Steam , gas, combined cycle, diesel engine, generated unit as per following formula;

 

GOF

=

Gross Actual Generation

X

100

Service Hours x Gross Maximum Capacity

 

                                                        

7- Reserved Capacity Factor -RCF

 

This must be calculated on quarterly basis during a year. It is needed to be calculated for all units (MWH) generated by, steam, gas, combined cycle, or diesel engine generating systems, as per following formula;

 

RCF

=

TAC @ 50 c - Import –System peak load

X

100

System peak load

 

8- Gross Heat Rate- GHR

 

This must be calculated on quarterly basis during a year. It is needed to be calculated for steam, gas, combined cycle, diesel engine, generating systems as per following formula;

 

GHR

=

(Fuel Consumed x Fuel Heating Value x Fuel SP. Gravity) + (Gas Consumed x Gas Heating Value x 1000)

X

100

Gross Actual Generation

 

·         Liquid fuel consumption is calculated in Cubic Meters M3 .

·         Gas consumption is calculated in Million Standard Cubic Foot (MMSCF).

·         Fuel oil heating value: calculate it by  (BTU)/KG i.e. British Thermal Units per Kilogram

·         Gas heating value: calculate it by BTU/SCF i.e. British Thermal Units per Standard Cubic Foot.

 


INSTRUCTIONS FOR GENERATING UNIT EVENT REPORTING

 

 

Planned Outage – PO

 

CASE  NO.1. If Operation & Maintenance Division request to shift, earlier, “an agreed planned outage period”; on a given unit:

 The (PO) period advancement would be carried out as  (PO) with the agreement of power plant, who can (before the commencement of unit planned outage), demand the same time period or different than what was previously assigned.

 

CASE NO.2. If Operation & Maintenance Division request the deferment, of, “an agreed planned outage period”; on a given unit:

The (PO) period deferment would be carried out as  (PO) with the agreement of power plant, who can (before the commencement of unit planned outage), demand the same time period or different than what was previously assigned.

 

CASE NO.3. If Operation & Maintenance Division request the advancement or deferment, of, “an agreed planned outage period”; on a given unit, and an extension in time period took place, without  changing the scope of work :

The (PO) period advancement or deferment would be carried out as  (PO), with the agreement of power plant, who can (before the commencement of unit planned outage), demand the same time period or different than what was previously assigned but if the job could not be completed on time then the unit will be entered into Scheduled Extension of Planned Outage (SE of PO) state till the completion of job.

 

CASE NO.4. If Operation & Maintenance Division request the advancement or deferment, of, “an agreed planned outage period”; on a given unit, and an extension in time period took place along with a change in scope of work :

The (PO) period advancement or deferment would be carried out as  (PO) with the agreement of power plant, who can (before the commencement of unit planned outage), demand the same time period or different than what was previously assigned but change in scope of work, delayed completion of job, then the unit will enter into forced outage immediate (U1), for a maximum period of 168 hours.

 

CASE NO.5. If a power plant requests to shift, “an approved planned outage time period” to an earlier date and Operation & Maintenance Division agrees:

 The (PO) period advancement would be carried out as (PO), for the same (previously) decided duration and power plant has no right to request a different duration than what was allocated in the original plan.

 

CASE NO. 6. If a power plant requests to defer, “an approved planned outage time period” to a later date and Operation & Maintenance Division agrees:

The (PO) period deferment would be carried out as  (PO), for the same (previously) decided duration and power plant has no right to request a different duration than what was allocated in the original plan.

 

CASE NO.7. If a power plant requests the advancement or deferment, of, “an agreed planned outage period”; on a given unit and Operation & Maintenance Division approves and later on an extension in time period takes place without changing the scope of work:

The (PO) period advancement or deferment would be carried out as  (PO), for the time period  as was previously assigned but  if  the job could not be completed on time then the unit will be entered Scheduled Extension of Planned Outage (SE of PO) state till the completion of job.

 

CASE NO.8: If power plant requests the advancement or deferment, of, “an agreed planned outage period”; on a given unit and Operation & Maintenance Division approves and later on an extension in time period takes place along with a change in scope of work:

The (PO) period advancement or deferment would be carried out as  (PO), for the time period  as was previously assigned but change in scope of work delayed the completion of job, then for the remaining period ,the unit will enter into forced outage immediate (U1), for a maximum period of 168 hours.

 

CASE NO.9: Without the approval of Operation & Maintenance Division:

If a power plant shifts, “an agreed planned outage time period” to an earlier date producing

  a gap, between new start date and original planned start date longer in duration than original PO  period.

Provided that:

1)      Job duration (new) is maintained equal to original PO period

2) The job completion date (new) falls before the predetermined planned start date.

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a maximum period of 168 hours, then unit will enter into Maintenance Outage (MO) state till the completion of job and there was no extension in the predetermined planned period.

Hence both periods U1 & MO, equal to scheduled PO period.

 

CASE NO.10: Without the approval of Operation & Maintenance Division:

If power plant shifts, “an agreed planned outage time period” to an earlier date producing a gap between new start date and original planned start date, lesser in duration than original PO period but greater than a week,

Provided that:

1)      Job duration (new) is maintained equal to original PO period

2)      The job completion date (new) falls after the predetermined planned start date

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a maximum period of 168 hours, then unit will enter into Maintenance Outage (MO) state for a duration till the predetermined planned start date and it will remain in PO till completion of planned job.

 Hence all periods, U1, MO & remaining PO equal to original scheduled PO.

 

CASE NO.11: Without the approval of Operation & Maintenance Division:

 If a power plant shifts an agreed planned outage time period” to an earlier date producing a gap between new start date and original planned start date lesser in duration than a week.

Provided that:

1) Job duration (new)  is maintained equal to original PO period

2) The job completion date (new) falls after the predetermined planned start date.

 

Resolution: The unit will be considered in forced outage (immediate) U1 till the   commencement of start date of Planned Outage (PO). Hence both periods U1and remaining PO will be equal to original scheduled PO period.

 

CASE NO.12: Without the approval of Operation & Maintenance Division:

    If a power plant shifts, “an agreed planned outage time period” to an earlier date producing

                     a gap between new start date and original planned start date, longer in duration than original PO  period. Additionally an extension in time period also takes place without changing the scope of work:

Provided that:

1) Job duration (new) is greater than original PO period.

   2) The job completion date (new) may fall after the predetermined planned start date.

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a period of 168 hours then unit will enter into Maintenance Outage (MO) state, and if job is not completed within predetermine PO period the rest of the job period will be considered as SE of MO.

 Hence periods U1& MO, will be equal to original scheduled PO period.

 

CASE NO.13: Without the approval of Operation & Maintenance Division :

If power plant shifts, “an agreed planned outage time period” to an earlier date producing a gap between new start date and original planned start date lesser in duration than original PO period but greater than a week,. Additionally, an extension in time period also takes place without changing the scope of work:

 Provided that:

1) Job duration (new) is greater than original PO period

2) The job completion date (new) falls after the predetermined planned start date

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a period of 168 hours, then unit will enter into Maintenance Outage (MO) state until the predetermined planned start date commences. Further it will enter into PO. And if job not finished during predetermined planned period then the unit will be considered in SE of PO. Hence periods, U1, MO & remaining PO equal to original scheduled PO period.

 

CASE NO.14: Without the approval of Operation & Maintenance Division :

If power plant shifts, “an agreed planned outage time period” to an earlier date producing a gap between new start date and original planned start date lesser in duration by one week,. Additionally, an extension in time period also takes place without changing the scope of work:

 Provided that:

1) Job duration(new)  is greater than original PO period

2) The job completion date (new) falls after the predetermined planned start date

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a period up to the start of original scheduled PO date, then unit will enter into Planned Outage (PO) from the start of PO period, till the end of the predetermined planned period then if job is not completed requiring more time, the unit will be considered in SE of PO.

Hence periods, U1& remaining PO equal to original scheduled PO period.

 

CASE NO.15: Without the approval of Operation & Maintenance Division :

If power plant shifts, “an agreed planned outage time period” to an earlier date producing a gap, between new start date and original planned start date longer in duration than original PO period. Additionally, an extension in time period also takes place along with changing the scope of work.

Provided that:

1) Job duration(new) is greater than original PO period

2) The job completion date (new) falls after the predetermined planned start date

Resolution: The unit will be considered in forced outage (immediate) U1 for a maximum period of 168 hours, then unit will enter into Maintenance Outage (MO), in such a way that U1 +MO periods equal to predetermined planned period. If job is not completed requiring more time due to unforeseen scope of work, unit will be considered in second U1 for another maximum period of 168hours. If still job completion requires more time another MO will be allocated.

 Hence sum of periods, first U1& and first MO, equal to predetermined planned period.

 

CASE NO.16: Without the approval of Operation & Maintenance Division :

If a power plant shifts, “an agreed planned outage time period” to an earlier date producing       a gap between new start date and original planned start date lesser in duration than original PO period but greater than a week, Additionally, an extension in time period also takes place along with a change in the scope of work.

 Provided that:

1) Job duration (new) is greater than original PO period

2) The job completion date (new) falls after the predetermined planned start date

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a maximum period of 168 hours, then unit will enter into Maintenance Outage (MO) state until the predetermined planned start date commences. Further it will enter into PO in such a way that U1 +MO +( remaining PO periods), equal to predetermined planned period. If job is not completed requiring more time due to unforeseen scope of work, unit will be considered in second U1 for another maximum period of 168hours. Further, if still job completion requires more time, unit will enter into MO.

 

CASE NO.17: Without the approval of Operation & Maintenance Division :

If a power plant shifts, “an agreed planned outage time period” to an earlier date producing a gap, between new start date and original planned start date lesser in duration than a week. Additionally, an extension in time period also takes place along with a change in the scope of work.

 Provided that:

1) Job duration (new) is greater than original PO period

2) The job completion date (new) falls after the predetermined planned start date

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a period up to the start of original scheduled PO date, then unit will enter into Planned Outage (PO) from the start of PO period, till the end of predetermined planned period in such a way that first U1+ remaining PO equals total predetermined planned period, then if job is not completed requiring more time, due to unforeseen scope of work, unit will be considered in second U1 for another maximum period of 168hours. Further, if still job completion requires more time, unit will enter into MO.

 

CASE NO.18. With out the approval of Operation & Maintenance Division:

                  If a power plant defers, “an agreed planned outage time period” to a later date falling within   predetermined planned period and finishing the job within predetermined planned period.

   Provided that:

1) Job duration (new) is lesser than original PO period

                     2) The job completion date(new) is earlier or same as original completion date.

 

Resolution: The unit will be considered in (PO) for remaining predetermined planned period and power plant has no right to request a different duration than what was allocated in the original plan.

 

CASE NO.19. Without the approval of Operation & Maintenance Division:

If a power plant defers, “an agreed planned outage time period” to a later date falling after predetermined planned completion date,

   Provided that:

1) Job duration(new)  is equal to original PO period

                     2) The job starting date (new) is after the predetermined planned completion date.

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a maximum period of 168 hours, then unit will enter into Maintenance Outage (MO) state.

 Hence both periods U1 + MO,  equal to scheduled PO period.

 

CASE NO.20. With out the approval of Operation & Maintenance Division:

                     If a power plant defers, “an agreed planned outage time period” to a later date falling within predetermined planned period and an extension also takes place with out changing the scope of work.

   Provided that:

                     The job starting date (new) is after the predetermined planned start date.

 

   Resolution: The unit will be considered in (PO) for remaining predetermined planned period and if the job completion requires more time keeping the scope of work same, unit will enter into SE OF PO.

 

CASE NO.21. Without the approval of Operation & Maintenance Division:

 If a power plant defers, “an agreed planned outage time period” to a later date falling after predetermined planned completion date and an extension also takes place with out changing the scope of  work :

   Provided that:

1) Job duration (new)  is longer than the original PO period

                     2) The job starting date (new) is after the predetermined planned completion date.

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a period of 168 hours, then unit will enter into Maintenance Outage (MO) state and if the job completion requires more time keeping the scope of work same, unit will enter into          SE OF MO.

 Hence periods U1& MO, will be equal to original scheduled PO period.

 

CASE NO.22. Without the approval of Operation & Maintenance Division:

If a power plant defers, “an agreed planned outage time period” to a later date falling after predetermined planned start date, within the PO period along with a change in scope of work.

Provided:

1) Job duration (new) is the same as original PO period

                     2) The job starting date (new) is after the predetermined planned start date.

 

Resolution: The unit will be considered in (PO) for remaining predetermined planned period and changed scope of work requires more time for completion, therefore unit will be in U1 for   a maximum period of 168 hours. Further if more time period is required for completion, unit will enter into MO, in such a away that total of remaining PO period, U1 and MO equals   to predetermined planned period.

 

CASE NO.23. Without the approval of Operation & Maintenance Division,

 If a power plant defers, “an agreed planned outage time period” to a later date falling before predetermined planned completion date and within the PO period. An extension also takes place along with a change in the scope of work:

   Provided that:

1) Job duration (new) is longer than the original PO period

                     2) The job starting date (new) is after the predetermined planned start date.

 

Resolution: The unit will be considered in (PO) for remaining predetermined planned period and changed scope of work requires more time for completion, therefore unit will be in U1 for  a period of 168 hours. Further if more time period is required for completion, unit will enter into MO in such a way that remaining PO+U1+MO equals to predetermined planned period. But if still job is not completed, the unit will be considered as SE of MO.

 

CASE NO.24. Without the approval of Operation & Maintenance Division, if a power plant defers, “an agreed planned outage time period” to a later date falling after predetermined planned completion date and an extension also takes place along with a change in the scope

of work :

   Provided that:

1) Job duration is longer than the original PO period

                     2) The job starting date (new) is after the predetermined planned completion date.

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a  period of 168 hours, then unit will enter into Maintenance Outage (MO) state such that       first U1 + MO  Equals predetermined planned period and if the job completion requires more time due to change in the scope of work, unit will enter into an other U1 for a maximum period of 168 hours.

 

MAINTENANCE OUTAGE –(MO)

 

CASE NO.1. If Operation & Maintenance Division request to shift, earlier, “an agreed Maintenance Outage period”; on a given unit:

 The (MO) period advancement would be carried out as  (MO) with the agreement of power plant, who can (before the commencement of unit Maintenance Outage), demand the same time period or different than what was previously scheduled.

  

CASE NO.2. If Operation & Maintenance Division request the deferment, of, “an agreed Maintenance Outage period”; on a given unit:

The (MO) period deferment would be carried out as  (MO) with the agreement of power plant, who can (before the commencement of unit Maintenance Outage), demand the same time period or different than what was previously scheduled.

 

CASE NO.3. If Operation & Maintenance Division request the advancement or deferment, of, “an agreed Maintenance Outage period”; on a given unit, and an extension in time period took place, without changing the scope of work:

The (MO) period advancement or deferment would be carried out as  (MO), with the agreement of power plant, who can (before the commencement of unit Maintenance Outage), demand the same time period or different than what was previously scheduled.

But if the job could not be completed on time then the unit will be entered into Scheduled Extension of Maintenance Outage (SE of MO) state till the completion of job.

 

CASE NO.4. If Operation & Maintenance Division request the advancement or deferment, of, “an agreed Maintenance Outage period”; on a given unit, and an extension in time period took place along with a change in scope of work:

The (MO) period advancement or deferment would be carried out as  (MO) with the agreement of power plant, who can (before the commencement of unit Maintenance Outage), demand the same time period or different than what was previously scheduled but change in scope of work, delayed completion of job, then the unit will enter into forced outage immediate (U1), for a maximum period of 168 hours.

 

CASE NO.5. If power plant requests to shift, “an approved Maintenance Outage period” to an earlier date and Operation & Maintenance Division agrees:

 The (MO) period advancement would be carried out as (MO), for the same (previously) scheduled duration and power plant has no right to request a different duration than what was scheduled in the original plan.

 

CASE NO. 6. If power plant requests to defer, “an approved Maintenance Outage time period” to a later date and Operation & Maintenance Division agrees:

The (MO) period deferment would be carried out as  (MO), for the same (previously) scheduled duration and power plant has no right to request a different duration than what was scheduled in the original plan.

 

CASE NO.7. If power plant requests the advancement or deferment, of, “an approved Maintenance Outage period”; on a given unit and Operation & Maintenance Division agrees and later on an extension in time period takes place without changing the scope of work:

The (MO) period advancement or deferment would be carried out as  (MO), for the time period  as was previously scheduled but  if  the job could not be completed on time then the unit will be entered into Scheduled Extension of Maintenance Outage (SE of MO) state till the completion of job.

 

CASE NO.8: If power plant requests the advancement or deferment, of, “an approved Maintenance Outage period”; on a given unit and Operation & Maintenance Division agrees and later on an extension in time period takes place along with a change in scope of work:

The (MO) period advancement or deferment would be carried out as  (MO), for the time period as was previously scheduled but change in scope of work delayed the completion of job, then for the remaining job period, the unit will enter into forced outage immediate (U1), for a maximum period of 168 hours.

 

CASE NO.9: Without the approval of Operation & Maintenance Division:

If a power plant shifts, “an agreed Maintenance Outage time period” to an earlier date producing a gap, between new start date and original scheduled start date, greater, equal or less in duration as original MO period.

Provided that:

1)      Job duration (new) is maintained equal to original MO period

2) The job completion date (new) falls before or after the predetermined scheduled start date.

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a maximum period of 168 hours or till the commencement of MO begins, which ever is earlier, then unit will enter into Maintenance Outage (MO) state till the completion of job.

Hence both periods U1 & (remaining MO period), equal to scheduled MO period.

 

CASE NO.10: Without the approval of Operation & Maintenance Division:

If power plant shifts, “an agreed Maintenance Outage time period” to an earlier date and an extension takes place without changing scope of work.

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a maximum period of 168 hours, or till the commencement of MO begins, which ever is earlier, then unit will enter into Maintenance Outage (MO) state till the completion of job.

But if job is not completed within the originally scheduled MO period, requiring more time with out changing scope of work, then unit will be considered in SE of MO.

 Hence periods, U1, & remaining MO period equal to original scheduled MO period.

 

CASE NO.11:. Without the approval of Operation & Maintenance Division:

If power plant shifts, “an agreed Maintenance Outage time period” to an earlier date and an extension takes place along with a change in scope of work.

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a maximum period of 168 hours, or till the commencement of MO begins, which ever is earlier, then unit will enter into Maintenance Outage (MO) state up till the originally scheduled MO period. After wards due to change in scope of work, the unit will be considered in another U1 for a maximum period of 168 hours, if still require more time to complete the remaining job , then another MO will be allocated.

 Hence periods, first U1, & first (remaining MO) period equal to original scheduled MO period.

 

CASE NO.12: Without the approval of Operation & Maintenance Division:

                  If a power plant defers, “an agreed Maintenance Outage time period” to a later date falling within the predetermined Scheduled period and finishing the job within predetermined Scheduled period.

   Provided that:

1) Job duration (new) is lesser than original MO period

                     2) The job completion date (new) is same as original completion date.

 

Resolution: The unit will be considered in (MO) for remaining predetermined scheduled period and power plant has no right to request a different duration than what was allocated in the original plan.

   

CASE NO.13: Without the approval of Operation & Maintenance Division:

If a power plant defers, “an agreed Maintenance Outage time period” to a later date falling after predetermined scheduled completion date,

   Provided that:

1) Job duration (new) is equal to original MO period

                     2) The job starting date (new) is after the predetermined scheduled completion date.

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a maximum period of 168 hours, then unit will enter into Maintenance Outage (MO) state.

 Hence both periods U1 + (remaining MO period) ,  equal to scheduled MO period.

 

CASE NO.14: Without the approval of Operation & Maintenance Division:

If a power plant defers, “an agreed Maintenance Outage time period” to a later date falling within the predetermined Scheduled period then an extension takes place with out a change in scope of work.

   Provided that:

                         The job starting date (new) is after original job starting date.

 

Resolution: The unit will be considered in (MO) for remaining predetermined scheduled period and if job not finished, then unit will enter into SE of MO.

 

CASE NO.15: Without the approval of Operation & Maintenance Division:

If a power plant defers, “an agreed Maintenance Outage time period” to a later date falling after predetermined scheduled completion date, then an extension takes place with out a change in scope of work.

   Provided that:

                      The job starting date (new) is after the predetermined scheduled completion date.

 Resolution: The unit will be considered in forced outage (immediate) U1 for a maximum period of 168 hours, then unit will enter into Maintenance Outage (MO) state. But if job is not completed within the originally scheduled MO period, requiring more time with out changing scope of work, then unit will be considered in SE of MO.

                      Hence both periods U1 + (remaining MO period) ,  equal to scheduled MO period.

 

CASE NO.16: Without the approval of Operation & Maintenance Division:

If a power plant defers, “an agreed Maintenance Outage time period” to a later date falling after predetermined scheduled start date, within the MO period along with a change in scope of work.

Provided:

1) Job duration (new) is the same as original MO period

                     2) The job starting date (new) is after the predetermined Maintenance Outage start date.

 

Resolution: The unit will be considered in (MO) for remaining predetermined Maintenance Outage period and changed scope of work requires more time for completion, therefore unit will be in U1 for a maximum period of 168 hours. Further if more time period is required for completion, unit will enter into 2nd MO, in such a away that total of remaining MO period, U1 and 2nd MO equals to predetermined Maintenance Outage period.

CASE NO.17: Without the approval of Operation & Maintenance Division,

 If a power plant defers, “an agreed Maintenance Outage time period” to a later date falling before predetermined scheduled completion date and within the MO period. An extension also takes place along with a change in the scope of work:

   Provided that:

1) Job duration (new) is longer than the original MO period

                     2) The job starting date (new) is after the predetermined Maintenance Outage start date.

 

Resolution: The unit will be considered in (MO) for remaining predetermined Maintenance Outage period and changed scope of work requires more time for completion, therefore unit will be in U1 for a maximum period of 168 hours. Further if more time period is required for completion, unit will enter into 2nd MO in such a way that remaining 1st MO+U1+2nd MO equals to predetermined Maintenance Outage period. But if still job is not completed, the unit will be considered as SE of MO.

 

CASE NO.18. Without the approval of Operation & Maintenance Division:

                     If a power plant defers, “an agreed Maintenance Outage time period” to a later date falling after predetermined scheduled completion date and an extension also takes place along with a change in the scope.

   Provided that:

1) Job duration is longer than the original MO period

                     2) The job starting date (new) is after the predetermined Maintenance Outage completion date.

 

Resolution: The unit will be considered in forced outage (immediate) U1 for a maximum period of 168 hours, then unit will enter into Maintenance Outage (MO) state such that       first U1 + MO Equals predetermined Maintenance Outage period and if the job completion requires more time due to change in the scope of work, unit will allocated an other U1 for a maximum period of 168 hours.

 

Reserved Shut Down State

 

CASE NO.1

Unit was in state of RS , demanded by System Control, unit started and synchronized with the System Network  successfully, there after unit entered into state  of (SH).

 

CASE NO.2

Unit was in state of RS and PO time commences, therefore unit entered into PO state.

 CASE NO.3

Unit was in state of RS and MO time commences, therefore unit entered into MO state.

 CASE NO.4

 Unit was in state of RS and Control demanded for synchronization with System Network, but Start Failure appeared, therefore unit entered into SF state for a maximum period of 168 Hours.

 CASE NO.5

Unit was in state of RS and Control demanded for synchronization with System Network, but Start Failure appeared. The unit entered into SF state for a maximum period of 168 Hours but trouble could not be resolved within 168 Hours thereafter unit entered into Maintenance Outage(MO).

 CASE NO.6

 Unit was in state of RS and during RS some maintenance was carried out , creating no hurdle for unit to be synchronized  with  System Network, therefore unit remained in the state of RS .

 CASE NO.7

 Unit was in state of RS and during RS some maintenance was carried out , and as a result of maintenance work unit could not be  synchronized  with  System Network, therefore unit state (RS) transformed to Unplanned Forced Outage (U1) for a maximum period of 168 Hours.

 CASE NO.8

 Unit was in state of RS and during RS some maintenance was carried out , and as a result of maintenance work unit could not be  synchronized  with  System Network, therefore unit state (RS) transformed to Unplanned Forced Outage (U1) for a period of 168 Hours  and still unit could be made ready for synchronization, then the unit would be considered in MO State.

 

Unplanned Forced Outage

CASE NO1: Unit Remained In Either Of U1, U2, U3 For 168 Hours Continuously:

If a unit remains in any Unplanned Forced outage (U1, U2 , U3) for 168 hours continuously, there the fore unit state must  be changed from (U1, U2 ,U3)  to MO .

  CASE NO2: Due to some trouble, taking unit out of Service Immediately or Transfer from other Outage States, including RS as U1.

Prevailing state of the unit be Finished and declare the unit in Unplanned forced Outage Immediately (U1) for a maximum period of 168 hours.

 CASE NO3: Due to some trouble, Taking unit out of Service Within 6 Hours by informing Operation & Maintenance Division and System Control:

 Due to some trouble if a unit requires immediate removal from the in-service state within next 6 hours, inform Operation & Maintenance Division and System  Control and put the unit into  Unplanned  Forced Outage  (U2) for a maximum period of 168 hours.

 CASE NO4: Due to some trouble, Taking unit out of Service After 6 Hours by informing Operation & Maintenance Division and System Control:

 Due to some trouble if a unit requires immediate removal from the in-service state after next 6 hours, inform Operation & Maintenance Division and System  Control and put the unit into  Unplanned  Forced Outage  (U3) for a maximum period of 168 hours.

 

CASE NO5: Unit Recovered from Either of (U1, U2, U3) and not required by System Control for Operation:

If a unit remains in any Unplanned Forced outages (U1, U2, U3) for less than or equal to 168 hours and trouble had been removed before the laps of 168hours, terminate the Prevailing State(U1, U2, U3) of the unit  and declare the unit in RS if not required by the System Control for operation.

 

CASE NO 6: Unit Recovered from Either of (U1, U2, U3) and required by System Control for Operation:

If a unit remains in any Unplanned Forced outages (U1, U2, U3) for  less than or equal to 168 hours and trouble had been removed  before the laps of 168hours, terminate the Prevailing State(U1, U2,U3) of the unit  and Operate normally  for System Control, declaring the unit in SH.

 

CASE NO 7: Unit Recovered from Either of (U1, U2, U3) and required by System Control for Operation but unable to synchronize after start-up:

If a unit remains in any Unplanned Forced outages (U1, U2 , U3) for  less than or equal to 168 hours and trouble had been removed  before the laps of 168hours , terminate the Prevailing State(U1,U2,U3) of the unit  and unit was required to be placed on line but could not reach synchronization, enter the  unit into SF for a maximum period of  168 hours.

 

 

CASE NO 8If a unit is in Unplanned Forced Outage (UX-1) and during that period another Unplanned Forced Outage (UX-2) occurs.  

Consider the unit in Unplanned Forced Outage (UX-1) till the removal of trouble or up to 168 hours maximum and Unplanned Forced Outage (UX-2) will not be considered.

 

CASE NO 9If a unit is in Unplanned Forced Outage (UX-1) and during that period another Unplanned Forced Outage (UX-2) occurs and (UX-1) crosses 168 hours.

   Consider the unit in Unplanned Forced Outage (UX-1) state for specified maximum168 hours and if the cause of (UX-1) is not being resolved, then place the unit in Maintenance Outage (MO) state although another Unplanned Forced Outage (UX-2) had occurred which will not be considered.

 

CASE NO 10: If a unit is in Unplanned Forced Outage (UX-1) and during that period another Unplanned Forced Outage (UX-2) occurred, but resolved before the laps of Unplanned Forced Outage (UX-1) time period.

Consider the unit in Unplanned Forced Outage (UX-1) till the removal of trouble or up to 168 hours maximum and Unplanned Forced Outage (UX-2) will not be considered.

 CASE NO 11: If a unit is in Unplanned Forced Outage (UX-1) and during that period another Unplanned Forced Outage (UX-2) occurred, resolved before the laps of (UX-1) period which is greater than 168 hours.

Consider the unit in Unplanned Forced Outage (UX-1) state till the resolution or for specified maximum168 hours and if the cause of (UX-1) is not being resolved, then place the unit in Maintenance Outage (MO) state although another Unplanned Forced Outage (UX-2) had occurred and resolved before the laps of (UX-1) allocated period, hence (UX-2) will not be considered in this case.

 

CASE NO 12: If a unit is in Unplanned Forced Outage (UX-1) and during that period another Unplanned Forced Outage (UX-2) occurred & not resolved (UX-2) before the laps of (UX-1).

Consider the unit in Unplanned Forced Outage (UX-1) state till the resolution or and if the cause of (UX-1) has been resolved and the cause of  (UX-2) has not been resolved then place the unit in Unplanned Forced Outage (UX-2) in such a way that time period of (UX-1) &

Remaining (UX-2) equal to 168 hours maximum. Record the (UX-2) starting from end of (UX-1) time period.

 

CASE NO 13: If a unit is in Unplanned Forced Outage (UX-1) and during that period another Unplanned Forced Outage (UX-2) occurred & not resolved (UX-2) before the laps of (UX-1) time, crossing the maximum limit of 168 hours.

 

Consider the unit in Unplanned Forced Outage (UX-1) state till resolution of its cause, and if the cause of  (UX-2) has not been resolved then place the unit in Unplanned Forced Outage (UX-2) in such a way that:

 Total time periods of (UX-1) & remaining of (UX-2) equal to 168 hours maximum. If still the cause of (UX-2) requires more time for its resolution, consider the unit in Maintenance Outage (MO). Record the (UX-2) starting from end of (UX-1) time period.

 

CASE NO14: Unit not recovered from Either of (U1, U2, U3) and commencement of Maintenance Outage MO begins.

Keep the unit in (U1, U2, U3) state till resolution of its cause or up to 168 hours maximum but if the commencement of MO period begins before the lapse of 168 hours consider the unit in MO from the start date of MO.

 

CASE NO15: Unit not recovered from Either of (U1, U2, U3) and commencement of Planned Outage PO begins.

Keep the unit in (U1, U2, U3) state till resolution of its cause or up to 168 hours maximum but if the commencement of the PO period begins before the lapse of 168 hours consider the unit in PO from the start date of PO.

  

START UP FAILURES (SF)

  

CASE NO 1: Unit Remained In Start-Up Failure For 168 Hours Continuously:

If a unit remains in Start-Up Failure (SF) for 168 hours continuously, there fore unit state must  be  changed from (SF )  to Maintenance Outage MO.

  

CASE NO2: Unit Recovered from Start-Up Failure (SF) and not required by System Control for Operation:

If a unit remains in Start-Up Failure (SF) for less than or equal to 168 hours and trouble had been removed before the laps of 168hours terminate the Prevailing State (SF) of the unit and declare the unit in RS if not required by the System Control for operation.

 

CASE NO 3: Unit Recovered from Start –Up Failure (SF) and required by System Control for Operation:

If a unit remains in Start –Up Failure (SF) for less than or equal to 168 hours and trouble had been removed before the laps of 168 hours , terminate the Prevailing State(SF) of the unit  and Operate normally  for System Control , declaring the unit in SH.

 

CASE NO 4: If a unit is in Start –Up Failure (SF-1) and after its resolution unit started, during the Start –Up we encountered another failure i.e. (SF-2) occurred .

Consider the unit in Start –Up Failure (SF-1) state till the resolution of cause of

(SF-1) and unit started but failed for second time. Therefore encountered SF-2 can be allocated a time period in such a way that time periods for

 (SF-1) + (SF-2)= 168 (maximum) hours. If the job still remain incomplete, unit will be scheduled as MO.

 

CASE NO 5: If a unit is in Start –Up Failure (SF) and during that period Encountered a trouble disallowing to Re-start & resolved the before the laps of (SF).

Declare the unit Start –Up Failure (SF) state till the resolution or for a maximum period of 168 hours. If cause of SF not rectified within 168 hours, consider the unit in MO. Since U1 was resolved before laps of SF time period, hence will not be considered.

 

CASE NO 6: If a unit is in Start –Up Failure (SF) and during that period Encountered a trouble disallowing to Re-start & not resolved before the laps of (SF).

Declare the unit Start –Up Failure (SF) state till the resolution or for a maximum period of 168 hours. If cause of secondary encountered trouble not rectified within remaining of 168 hours, then consider the unit in MO. Since U1 was not resolved before laps of SF time period, hence time periods of (SF+ U1) will be equal to 168 hours.

Record the (U1) starting from end of (SF) time period.

 

CASE NO 7: If a unit is in Start –Up Failure (SF) and commencement of Maintenance Outage (MO) begins.

Keep the unit in (SF) state till resolution of its cause or up to 168 hours maximum but if commencement of MO period begins before the lapse of 168 hours consider the unit in MO from the start date of MO.

 

CASE NO 8: If a unit is in Start –Up Failure (SF) and commencement of Planned Outage (PO) begins.

Keep the unit in (SF) state till resolution of its cause or up to 168 hours maximum but if commencement of PO period begins before the lapse of 168 hours consider the unit in PO from the start date of PO.

 

 

 

 


No comments:

Post a Comment