POWER PLANT
Content:
This report contains a description of the guidelines for preparing the monthly statistical report for power plants and includes the following:
1- Definition of the monthly statistical report.
2- The purpose of the monthly statistical report.
3- Instructions for preparing the monthly report.
report
1- Definition of the monthly statistical report for generating stations:
It is a set of forms in which detailed statistical information is recorded for the units and equipment of generating stations.
2- The purpose of the monthly statistical report for the power plants:
The purpose of the report is to build an integrated statistical database on the generation plants that are requested from time to time from other agencies and departments, in addition to unifying the source and form of data, which leads to accurate planning for the generation sector for the coming years.
3- Instructions for preparing the monthly report:
3-1: In the first four days of each month, the generation stations prepare the monthly report by filling in the following forms:
3-1-1: Monthly station summary form. This form is denoted by the symbol F1.
3-1-2: The monthly operational data model for the units, and this model is denoted by the symbol F2.
3-1-3: The monthly summary form of the units' operating hours when connecting with the exchanger to cool the air entering the units. This model is denoted by the symbol F3 for the Buraidah station and the symbol F4 for the eighth station.
3-1-4: The monthly operating hours model for compressors and exchangers. This model is denoted by the symbol F5 for the Buraydah station and the symbol F6 for the eighth station.
3-2: The stations send the report by e-mail to the Operation and Maintenance Planning Department on the fifth day of every month.
3-3: The Operation and Maintenance Planning Department checks and verifies the accuracy of the data recorded in the report and sends it back to the stations to avoid errors and notes, if any, before the ninth day of each month.
3-4: On the tenth day of each month, the Operation and Maintenance Planning Department works on extracting operational indicators.
3-5: From the tenth to the fifteenth day of each month, the Operation and Maintenance Planning Department prepares the monthly statistical report for the generation stations by filling out the following forms:
3-5-1: The installed capacity model in generating stations, and this model is symbolized by the symbol F8.
3-5-2: The operational status model for the generation stations, and this model is denoted by the symbol F9.
3-5-3: Model of available capacity and loads in generating stations. This model is symbolized by the symbol F10.
3-5-4: The model of the generated and transmitted energy, and this model is denoted by the symbol F11.
3-5-5: Model of fuel consumed in a generation, and this model is symbolized by the symbol F12.
3-6: On the fifteenth day of every month, the report is sent to the obstetrics coordinator at the Services Department.