3.3
TESTS ON SITE, RECORDS
TRAINING AND MAINTENANCE
PART
1 TEST ON SITE
3.3.1.1
GENERALLY
Carry out inspection and acceptance
tests on site on each complete system, before final placement into service, in
accordance with the Regulations and Standards, as described in the
Specification and required by the Engineer.
3.3.1.2 TEST SCHEDULES AND PROCEDURES:
Are
to be submitted for approval and are to include details of testing equipment to
be provided.
3.3.1.3 WITNESSING:
Inspection
and acceptance tests are to be carried out in the presence of the Engineer and,
when required, by an authorized representative of the Local Power Authority.
3.3.1.4 VISUAL INSPECTION
Visually
check proper installation, connections and nameplate data before testing.
3.3.1.5 INSULATION RESISTANCE
Test
feeders, lighting and power circuits, motors and other power equipment of low voltage installations
with a megger of not less than1000 V
operating voltage for 380/220 V to 600 V
systems and as required by the particular Section of the Specification.
3.3.1.6 INSULATION RESISTANCE
Unless
otherwise specified or approved, test circuit insulation resistance related to
communications and security systems with a megger of not less than 500 V
operating voltage, with equipment disconnected.
3.3.1.7 CONTINUITY
Test
all feeders and circuits for continuity.
3.3.1.8
OPERATIONAL TESTS
Carry
out operational tests on all equipment and complete systems to verify proper
performance in compliance with the specification. Operational tests are to be carried out under
normal operating conditions for not less than 3 days, and as required by the
Engineer.
3.3.1.9 SPECIFIC TESTS
Carry
out specific tests required by the Specification and any other tests required
by the Engineer to verify compliance of the installations with the
Specification.
RART
2
RECORDS
3.3.2.1 GENERALLY
Not
later than the date of substantial completion, provide the Engineer with four copies of all approved
as-installed drawings, test records,
manufacturers' guarantees and warranties, operating and maintenance manuals and
other records required by the
Specification.
3.3.2.
PRESENTATION
Of
records is to be in A4 size plastic covered, loose-leaf ring binders or other
approved binders with hard covers, each indexed, divided and appropriately
cover titled. Drawings larger than A4
size are to be folded and accommodated in the binders so that they may be
unfolded without being detached from the rings.
3.3.2 AS-INSTALLED DRAWINGS
Are
to contain the complete assembled information included on the construction
drawings, prepared in the same manner, and up-dated to indicate the systems,
labeling, referencing, mounting methods, routing etc. as installed. Submit complete drawings for approval. Provide the Engineer with one set of
transparencies in addition to the four copies required.
3.3.2. TEST RECORDS
Are
to include test certificates of type tests, routine tests, site tests,
commissioning and performance tests and all other tests on equipment and
installations described in the Specification and required by the Engineer. Include in formation regarding test
procedures and results, conditions under which tests were carried out including
set points, temperatures and he like, dates, location and attendance by
authorized representatives etc.
3.3.2.5 OPERATING AND MAINTENANCE
MANUALS:
Are
to contain the following:
- Technical
description of each system and item of equipment installed, written to ensure
that the Employer's staff fully understand the cope and facilities provided
- Diagrammatic
drawings of each system indicating principle components and items of equipment
- Schedules
(system by system) of equipment installed giving manufacturer, catalogue list
numbers, model, rating, capacity and Operating characteristics; each item is to
have a unique code and umber, cross- referenced to the diagrammatic drawings
and layout drawings
- Name,
address, telephone, telex and fax numbers of the manufacturer of every item of
equipment name, address, telephone and telex numbers of equipment
agents/representatives for emergency services and procedures.
- Manufacturer's
service manual for each major item of equipment assembled specifically for the
project, including detailed drawings, illustrations, circuit details, operating
and maintenance instructions, modes of operation, control provisions, sequences
and inter locks, and preventive maintenance programs
- Schedules
of all fixed and variable equipment settings establish during commissioning
- Procedures
for fault finding, where applicable
- Manufacturers'
lists of recommended spare parts subject to wear and deterioration, and expected
running period, indicating specifically those items which may involve extended
deliveries.
3.3.2.6 OPERATING AND MAINTENANCE MANUALS:
Prepare two temporary copies with provisional
record drawings and preliminary performance data and make available at time of
testing and commencement of commissioning to enable the Employer's staff to
familiarize themselves with the installations.
These should be of the same format as the final manuals with temporary
insertions for items which can not be finalized until the installations are
commissioned and performance tested.
PART
3 TRAINING
3.3.3.1 OPERATION AND MAINTENANCE TRAINING
Before the date of substantial completion,
explain and demonstrate to the
employer’s maintenance staff the purpose,
function and operation of the installations including all items and procedures listed in the operating
and maintenance manuals. Include for not less than 15 days for this
purpose.
PART
4 MAINTENANCE
3.3.4 MAINTENANCE CONTRACTS
Where required by the Specification, submit supplementary
proposals for annual maintenance contracts. The proposals should: (Include for
maintaining the installations in efficient working order including routine and
emergency service checks, adjustments, lubrication and supply and replacement
of damaged parts etc.
- Set
out the terms of the offer, the work to be carried out, the guarantees of
performance and the price for the first twelve months after substantial
completion of the work or part thereof the work or part thereof.
The proposals will not be considered
as part of the tender.
End Of This Section
No comments:
Post a Comment