MEDUIM
VOLTAGE SWITCHGEAR&
INDOOR TRANSFORMER SUBSTATION
PART 1 GENERAL
3.4.1.1 RELATED DOCUMENTS
a. Drawings and
general provisions of Contract, including
General and special Conditions, General requirements apply to work of this section.
General and special Conditions, General requirements apply to work of this section.
b.
General Provisions for Electrical Work, Section 3.1, 3.2 apply to work of this
section.
3.4.1.2 DESCRIPTION OF WORK
Work
includes providing all materials, equipment, accessories, services and tests
necessary to complete and make ready for operation by the Owner, switchgear in accordance with Drawings and Specifications.
3.4.1.3 QUALITY ASSURANCE
A. Manufacturers: Firms regularly engaged
in the manufacture of switchgear of the types and capacities required, whose
products have been in satisfactory use in similar service for not less than 5
years.
B. Standards
Compliance: Comply with requirements of applicable local codes and DIN/VDE, and
IEC. Standards pertaining to switchgear. Provide service entrance label and
applicable service entrance features per local code and NEC· Provide switchgear
products and components which' have been UL listed
and labeled·
3.4.1.4 SUBMITTALS
a - Product data: Submit manufacturer’s data
for switchgear including sizes,
enclosures, and electrical ratings and characteristics.
b - Shop Drawings: Submit dimensional layout
on architectural background
drawings of switchgear, single-line diagram, and outline drawings.
C - Relay co-ordination:
Submit ready and circuit breaker
co-ordination study.
The
current-time characteristics must be plotted on a log-log papers showing that
the choice of the C.B. settings are correct for co-ordination.
D - Submit to Electricity distribution Co. for approval layout plans, risers and loading
schedules with medium voltage switchgear transformers and ring main units.
PART 2 PRODUCTS:
3.4.2.1 INSPECTION
A. Examine conditions under which
switchgears are to be installed Notify Architect in writing of conditions
detrimental to proper completion of the work; do not proceed with work until
unsatisfactory conditions have been corrected.
B. Routine works tests shall be carried
out at the manufacturers works in the presence of the consultant.
PART
3 INSTALLATION
A. Install switchgears as indicated accordance
with manufacturer's written instruction, requirements of applicable standards,
NECA's "Standard of Installation," and in accordance with recognized
industry practices to ensure that installation complies with requirements and
serves intended function
B. Coordinate
as necessary to interface installation of switchgear with other work.
C. Mount
the switchgear assembly on floor steel aligning channels elevated above floor
level by a concrete pad and as noted on drawings. Provide shims to achieve
level installation.
D. Insure
that switchgears are shipped in sections which can be fitted through the
structures available.
E. Bond together the switchgear structure,
sections and all
conduits terminating at same with a 120 ram 2 bare copper earth cables and connect to the switchgear earth bus and to the earthing loop as required. Provide conduits terminating at switchgear with Earthing Wedges of the required size.
conduits terminating at same with a 120 ram 2 bare copper earth cables and connect to the switchgear earth bus and to the earthing loop as required. Provide conduits terminating at switchgear with Earthing Wedges of the required size.
F. Tighten
electrical connectors and terminals including screws and bolts, in accordance
with equipment manufacturer's published torque tightening values for equipment
connectors. Where manufacturer's torquing requirements are not indicated,
tighten connectors and terminals to comply with tightening torques specified in
UL Standard 486A and B.
G. Provide insulation mat in front of
switchgear and rear of freestanding equipment and extend 30cm beyond ends.
H. Provide
protective covering during construction.
I. Touch up marred or scratched surfaces
to match original finish.
J. Provide fuses of the ratings indicated,
with one complete set of spare fuses for each rating.
K. Adjust
operating mechanism for free mechanical movement
3.4.3.4
FIELD QUALITY CONTROL
A. Upon completion of installation of
equipment and after circuitry has been energized, test equipment to demonstrate
compliance with requirements When possible, field-correct malfunctioning units,
then retest to demonstrate compliance; otherwise remove and replace with new
equipment and retest.
B. Prior
to energization of switchgears:
1. Megger check phase-to-phase and phase-to-ground
insulating resistance levels of conductors
2. Check switchboard for continuity and
for short circuits.
C. Set
all circuit breaker trip ratings for maximum coordination
With
upstream and downstream devices, including ground fault trips where supplied.
D. Subsequent to wire and cable hook-ups,
energize equipment and demonstrate functioning in accordance with requirements.
E. Open
and close load break switching devices under load.
3.4.3.4
PERSONNEL TRAINING
A. Building Operating Personnel Training:
Train Owner's building personnel in procedures for starting up, testing and
operating H.V. switchgear and auxiliary equipment. Furnish three operator's
manual providing installation and operating instructions for the H.V·
switchgear.
INDOOR TRANSFORMERS SUBSTATION
PART4 - PRODUCTS
3.4.3.1
GENERAL.
A.
Supply,
install and commission Transformers sub-station complete including:
- 22 KV ring main unit.
- Oil type Transformer(s).
- All necessary fixing and
connection equipment and accessories required for a complete and operable
system.
B. Ensure that the space allocated for the
medium voltage switchgear and the transformers is in accordance with the
requirements and supplied by the manufacturer. Any inaccuracy in the building
once built, shall be corrected as required and directed by the Consulting
Engineer and at no extra charge to the Employer.
3.4.3.2
RING MAIN UNITS
A. GENERAL
a- Each ring main unit comprises three
No., three-pole load break switch switches rated 630 Amps for incoming feeders
and one three-pole load break switch 630 A for the cable connected to the M.V.
switchgear.
(400A
for the cable connected to transformer)
b- Cable termination boxes shall be
provided for the incoming and outgoing, also for the feeder to the 22KV
switchboard, having the following characteristics:
c- Incoming and outgoing feeders, to be as
used by the Electric Power Distribution
Company, coordinate with local power authority in this respect.
The 22 KV switchboard feeder,
3-Core, XLPE insulated armoured with 240 sq.mm. Aluminum conductor.
B. TECHNICAL DATA:
The ring-main-unit shall fulfill the
following data
a. Type Load
break switch
b. Rated
voltage 22
Kv
c. Rated current :
- Transformer load break switch 400A
- Ring main load break switches 630 A.
d. Short circuit level 25KVA
e. Impulse
withstand voltage
1.2/50
u sec ( KV Peak) 75KV.
f. Rated
insulation level, one minute
Withstand
voltage, 1 min., 50 Hz. 35
KV
g. Fuse rating ( A ) As
indicated in the Drawings
.
MV switch gear (if needed by the
authority)
To
be with SF6 C.B. with the same specifications as above while ratings to be as
shown on the drawings
3.4.3.4
TRANSFORMERS.
A. Transformers shall be of the indoor
type, low losses, dry type, two
windings, four off- load taps 2 x 2.5%
on the high voltage side, in compliance with the requirements of IEC recommendation No. 76, parts 1 to 5
inclusive.
B. Transformer
data:
- Rating KVA as indicated in the drawings.
- Primary voltage 22000 Volts
- Secondary voltage 380 Volts
- Vector group Dyn 11
-
Off-load tapping +/2 x 2.5% (H.V.) of phases No.
-
Frequency 50 Hz
Ambient
temperature (average)
45
- Impedance at principle tapping 6
%
- Terminal
arrangements: H.V. cable box for
XLPE
insulated, armoured 3-core Alum. Cable, 3 x 240 mm2 cross section area.
- L.V suitable connection for cables
- Transformers shall be cooled by
natural air convection.
C. The transformers shall be equipped with
control units and temperature sensors in order to perform alarm, tripping and
controlling the ventilation fan installed in the transformer room.
D. The transformers shall be provided with
noise reduction support blocks in order to reduce the noise level.
E. Following tests shall be carried out
according to IEC standards and include:
a.
Turns-ratio test
b. Insulation tests between windings and
between windings and earth.
c. Induced high voltage test.
d. No-load losses test.
e. Short circuit test.
f. Winding resistance measurement.
g. Loading and heat test
h. Resistance of insulation to impulse
test.
3.4.3.4
EQUIPMENT DATA/SHOP DRAWINGS
A. Shop/construction drawings for
installations covered under this sub-section shall include but not be limited
to the following:
B. Construction and installation details
for the M.V. switchboards cables and transformers.
C. Front
elevation of switchboard, one line diagram showing
current and voltage transformers With ratios, instruments, switches, relays, trip ratings.
current and voltage transformers With ratios, instruments, switches, relays, trip ratings.
D. Floor plan and top views showing
locations of power and
control conduit, ground cable entries and size, location and arrangement of tie bus-way.
control conduit, ground cable entries and size, location and arrangement of tie bus-way.
E. Bill of material of switchgear summary
listing all major components.
F. Details of connection of cables to
transformers and main distribution boards.
G. Wiring and schematic diagrams of power,
control, relay, metering and similar circuits. The separate schematic diagrams
shall include complete three line diagrams of 22 kV ring main units, and all
instruments, switches, instrument
Transformers,
auxiliary contacts, relays and any other devices in this switchgear
H. Handling,
installation and assembly drawings.
J. Key interlocking scheme showing key
numbers and operations performed Dimensioned outline drawings and sectional
switchgear views.
K. The equipment data to be provided prior
to ordering any material covered by this Sub-section shall include but not be
limited to the following:-
L. Complete technical data on circuit
-breakers and other switchgear including data operating characteristics,
compliance with standards, dimensions and weights, detailed description,
operating mechanism etc.
M. Complete technical data on instrument
transformers, protective and auxiliary relays, measuring instruments including
manufacturer's catalogues, operating characteristics, operating curves,
detailed description etc.
N. Complete technical data on the
construction of the switchgear, with provision for expansion including manufacturer’s
catalogues.
3.4.3.5
ACCEPTABLE MANUFACTURERS
A.
EMG (EGYPT )
B. ABB ARAB (EGYPT )
Or
approved equal
PART 5 - EXECUTION
3.4.5.1
INSPECTION
A. Examine conditions under which
transformer substations are to be installed. Notify engineer in writing of
conditions detrimental to proper completion of the work Do not proceed with
work until unsatisfactory conditions have been corrected.
3.4.5.2 INSTALLATION
A. Install transformer substations as
indicated in accordance with manufacturer's written instructions, requirements
of applicable standards, and in accordance with Electricity Co and local
authority requirements to ensure that installation complies with requirements
and serves intended function.
B. Coordinate as necessary to interface
installation of
transformers with related switchboards and other work.
transformers with related switchboards and other work.
C. Tighten electrical connectors and
terminals, including screws and bolts, in accordance with equipment
manufacturer's published torque tightening values for equipment connectors.
D. Provide
protective covering during construction.
E. Touch-up marred or scratched surfaces
to match original finish.
F. Adjust fans when so furnished for free
mechanical movement.
3.4.5.3
FIELD QUALITY CONTROL
A. Upon
completion of installation of equipment, and after
circuitry has been energized, test equipment to demonstrate compliance with requirements. Where possible, correct malfunctioning units, then retest to demonstrate compliance; otherwise, remove and replace with new equipment and retest at no additional cost to Owner.
circuitry has been energized, test equipment to demonstrate compliance with requirements. Where possible, correct malfunctioning units, then retest to demonstrate compliance; otherwise, remove and replace with new equipment and retest at no additional cost to Owner.
B. Prior to energization of transformers
and related distribution equipment:
1. With manufacturer’s approval, perform
phase-to-phase and phase-to-earth insulation resistance tests utilizing a
megohmmeter with minimum test voltage output of 5,000 volts DC with a minimum
resistance of 25,000 megohms. The test duration shall be for 10 minutes with
resistance tabulated at 30 seconds, (1) minute and 10 minutes. Dielectric
absorption ratio and polarization index will be calculated.
2. Check transformers for continuity and
for short circuits.
3. Notify Architect of any abnormalities.
C. Subsequent to wire and cable hook-ups,
energize transformers and demonstrate functioning in accordance with
requirements.
D. Provide manufacturer's recommended DC
high potential test for transformers and verify acceptability of results prior
to energizing.
End
Of This Section
No comments:
Post a Comment