AL ARABIA PROJECT
Cairo - Suez - Cairo
10 ~ 14 February 2018
Index:
·
Works on Saturday 10 February 2018 Jeddah - Suez
· Works on Sunday 11 February 2018 Suez
·
Works on Monday 12 February 2018 Suez
·
Works on Tuesday 13 February 2018 Suez - Cairo
·
Works on Wednesday 14 February 2018 Cairo - Jeddah
· Recommendations
· Accessories:
1.
Letter to Smart not to meet the conditions of the initial receipt and to charge them the visit fees
2.
El Fath for paving roads
3.
Additional works for electromechanical contracting company
4.
Disclosure of Contractors' Benefits on 14 February 2018
Works on Saturday 10 February 2018 Jeddah - Suez
Jeddah was left after midnight and arrived at dawn to Cairo and headed directly to the project site in Suez to inspect the work and start receiving the ground floor and the first of the administrative building .. And follow the work of the other contractors in the project as requested by Mr. Amr Al-Quwatli and Dr. Mohammad Salah Mutbakani.
After arriving on Saturday to the site I toured the administrative building to take a look at some of the works during the last period in which I was absent from the development of the work and before the arrival of engineer Ibrahim Samir with the presence of his engineers in the site then attended the following:
Mr. Amr Al - Quwatli
Dr. Mohamed Salah Motbakani
Mr. John Greek Nationality
And accompanied them on a tour of the administrative building and went to a meeting with Eng. Ibrahim and engineers, in the presence of Engineer Drehem and also a preview of the work and show us the following:
Preview the works of Smart in the project of the administrative building project Suez of the Arab company
Major defects and observations and shortcomings of the project:
1: Engineering Notes:
1. No maps As Built Of the project according to engineering requirements
2. Mismatch of dimensions with operational maps on nature.
3. There were no inspection tables for the inspection rooms.
4. Mismatched interfaces with design.
The facade does not match the design adopted in openings, aluminum, lighting, umbrella and construction
2: Notes and defects of paint works:
1. Defects in the work of paints
2. Whiteness in the convergence of ceilings and porcelain in bathrooms.
3. The whiteness above the doors is bad.
4. Paint primer, paste and its disadvantages
3: Notes and disadvantages floorings:
1. Defects in the work of ministers
2. Drumming in some floors
3. Not completely grounding floors
4. The use of white rubies does not fit the floor
5. Do not remove plastic gratings and watering them
6. Poor tiling in some places.
7. Rooms and bathrooms
8. The work of tiling outside the borders of the doors.
9. Disadvantages of cutting floors
4: defects and notes of carpentry work
1. Do not paint up and down doors
2. The composite sealer to lock the door is shorter than required
3. There will be wood, floor and walls.
4. Non-matching wood finishing with the desired From the owner.
5. Do not adopt grips for doors or doors and doors
6. There is no Master Ki system at all.
7. The lack of a sabbaur lelbawab.
8. The bolt of doors does not have a pipe buried in the floors and wood and does not fall to the ground.
9. The silicon is missing at the ends of the wood and walls to protect against water
10.
There is no bumper for doors
11.
Tongue to lock hits the wood and does not touch the protection plate due to a mistake in the manufacture of the doors
12.
The poor drilling industry of the San and the locks in the woodwork were handcrafted in a rough manner
5: Disadvantages and notes in bathrooms and health work:
1. Disadvantages in the plumbing, knowing that I have not conducted water experiments for lack of time and the lack of maps for that
2. Disadvantages of tiling of walls and walls of bathrooms.
3. Do not weigh water outlets and drainage in the bathrooms
4. The heaters are not as requested in some of the apparent bathrooms.
6: defects and notes of electrical works:
1. Irregularity of power switches and poor installation
2. Light and light are less than required for standard offices in Lux.
3. Disadvantages of cable cables and cover
4. Luminance in the Corridor Guy is synchronized with the entrances as desired Note gypsum defects Wales
5. Electrical plates without stickers in the names of prekers and paper stickers are easy to remove
6. The use of plastic pipes for installation or installation within the work of wood does not comply with the code against fire and must be metal
7 : safe room:
1. Disadvantages of the vaulted room finishes
2. Disadvantages of cutting porcelline closures to cabinet door.
3. Re-paint and rust to the door of the safe
8: defects of the work of the security :
1. The silicon around the windows is not good
2. Grafiato waste on all marble windows.
3. Many mistakes in the bumper of metal doors
4. There are no leakage holes in the aluminum ducts
9: Office Cutouts:
1. Not to use the cutters agreed with the contractor according to the approved sample in the presence of the owner
2. Do not sign the cutouts on the maps as implemented
3. There is no silcon between the walls and the marble
4. The infidelity of glass for the cutters has many disadvantages
10: Other Observations and Disadvantages:
·
There is no isolation of plant ponds
·
Wazza and binding of the pillars with defects
·
Adjust the boxes of fire boxes
·
The light is neither bleached nor melted
·
Tendering in gypsum works in several places
·
A hood should be installed in the cafeteria
·
Stainless steel pipes and prints
·
Plaster spaces in front of the doors in the service drawer.
·
Non-symmetry of the marble in the doors of the terrace and the quality of the doors and doors and lighting
·
Poor work of the windows and openings and the way to deal with them in the tiles and the bishop
Works on Sunday 11 February 2018 Suez
The audit was conducted on the activities of Smart and in the presence of Eng. Drehem and the team of engineers of Smart and behind the engineer Ibrahim Samir for special reasons.
Most of the work carried out for the land role and the first was reviewed in light of the reality, with observations to vary the implementation of the operational maps provided and the lack of maps of what has already been implemented.
The above images are examples of defects and observations in the work of SMART in the ground floor and the first of the administrative building was revealed on Saturday and Sunday.
I have not been able to fully disclose the work of adaptation, health, electricity, etc .. from other works because of the lack of documents that were requested weeks before my departure from the gentlemen of the company Smart and business congestion for lack of time.
Works on Monday 12 February 2018 Suez
The following meetings were held with:
·
Fire Fighting Company:
By meeting Eng. Ibrahim of International Company, request the following:
·
Follow-up d. FRA to approve the documents submitted to him by the International Company for Security and Safety Systems for the adoption of documents from maps and catalogs of an element used in the project and all related to the implementation of the company mentioned
·
Gasoline work is similar
·
Tank fuel generator set up a tandem and conduct an experiment
·
Connect the administrative building to the fire network near the site
·
Analysis of water received from the device to ensure its validity for drinking.
·
It is possible to operate a small purification plant in each hangar to use drinking water if the water is not supplied by the device for that.
·
Drain the rain
·
The meeting was held with Mr. Yasser Essam regarding the drainage works of the rainwater and the solution for the treatment of water collection from the drainage of column pipes.
·
Extend the drainage columns of the rain water and pass the bank from under the Interlock to spend on the asphalt directly to avoid leaching to the inside.
·
Al - Mustafa Company
·
M. Mohamed Mostafa for the audience today and asked him to conduct the operating experience in my presence as well as the processing of all documents, catalogs and maps of the AS BUILT
·
El Fath Company
·
The contractor will submit a final draft for the business next week
·
Check the extract on the nature to limit the quantities of implementation
·
The notes and works required for the repair shall be released in minutes in the presence of the Contractor and a representative of the Owner.
·
The Contractor shall have a term to terminate the repair of such defects and agreed observations
·
The contractor submits the letter in writing from the machine and the Egyptian code allows the use of powder instead of sand for watering in the Interlock. In the event that this is not available, the contractor shall be required to sand in the watering as required
·
The contractor submitted the RMP 7 Extract on 12 February 2018 during the meeting.
·
In this report, the contractor's contractors were assigned to the contractors' section.
·
Electromechanical Contracting Co.
·
The meeting was held with Eng. Ahmed Wali and discussed the proposal to use the HID system to save the hanger
·
Roller doors and entrance gates
·
Study of the submitted maps and indicate their lack of readiness and validity to be AS BUILT And the lack of adequate information thereon.
·
The adoption of two missing documents with the adoption of d. Fara and make a discount on them by 15%
·
Initial delivery will be uniform for all contractors in the factory.
·
Request for disclosure of names of suppliers and materials used and specifications for maintenance and operation later
·
In this report, the contractor's contractors were assigned to the contractors' section.
Works on Tuesday 13 February 2018 Suez - Cairo
It was rained yesterday and was a good occasion to test modified drainage pipes that worked efficiently and did not need any new processors. And recommend a template for this amendment to paint and warehouse.
·
SMART Meeting :
Staff Building
· In the presence of Eng. Ibrahim Sameer today, the workers' building was inspected and Smart's proposal to implement the building was discussed
· Design modifications were made to the proposal submitted
· SMART will submit these amendments to the plans for approval before implementation.
· Not good treatment of the concrete was observed after casting
· Request for the determination of fracture samples for the blade and columns.
· Iron fountains by rust need attention.
Administrative building
·
With reference to the administrative building and accompanied by Eng. Samir Ibrahim and engineers, gave a quick look at the work of the building in the third and fourth floors to avoid the defects of existing work in anticipation of repeated mistakes in the first and ground floor
·
Cracks in the work of Elias
·
Poor insulation and poor drainage
·
Rust has been observed in the iron of the elevator in the metal structure, which requires treatment in a pre-directional manner to avoid impregnation of the project near the sea
The site was left before Morocco heading to Cairo
Works on Wednesday 14 February 2018 Cairo - Jeddah
According to the decision, the meeting was held in the morning in the lobby lobby in Cairo with Mr. Ahmed Khalifa to consider the required payments to contractors, due to the absence of several months to follow up their payments and to report what is disbursed to them.
The review was conducted and a report was made to them in agreement with him.
After finishing, they sent me to the airport to leave for Jeddah.
with greetings
Talal Abdul Jalil Asaad M.
· Recommendations
· No benefits should be paid to Smart on the administrative building other than the payment of 500 thousand pounds agreed upon in the attached statement with Mr. Ahmed Khalifa
until the completion of the observations of the first and second roles and to ensure the right of the owner as the remaining amount barely covers the completion of work and repairs and defects.
· In order to avoid payments of Smart's work to the employees' premises or others,
but with caution to ensure the conduct of business.
· Smart requests good handling of the concrete in the workers' building and provides maps of the modifications discussed at the site for adoption. Concrete breakout reports are required.
·
SMART does not comply with some of the agreed materials, work without approved maps, and lack of detailed details, changes, errors and notes that need to be repaired or rebates from the contractor.
·
Smart is required to set a new date for initial receipt of the first and fourth floor with all required documents. And set an appointment to finish the notes
·
Al-Mustafy Company has to re-test the operation with my presence and provide the necessary maps and documents
· Al-Fath It is necessary to check the quantities and follow-up the reforms and reject the powder as an alternative to sand unless you provide written documents from the device and the Egyptian code.
· The Electro Mechanical Contracting Company is required to provide maps and documents for all the works carried out by it.
·
I have to receive a daily report on the progress of the work on the site for daily follow-up to any errors during the implementation since it is not worth sending pictures only once or twice a month.
Accessories
1.
Letter to Smart not to meet the conditions of the initial receipt and to charge them the visit fees
2.
El Fath for paving roads
·
Abstract 7 is ongoing
·
Extract No. 6
3.
Additional works for electromechanical contracting company
After conducting the discount and review
4.
Disclosure of Contractors' Benefits on 14 February 2018