 power plant

Slop -  
 Drain System
     -    A slop/drain system complete in all respects shall be provided comprising an underground slop tank and pumps to receive the drains from the system and pumps it to the oily water system.


The slop tank shall be made of concrete as per applicable owner standard.
Slop tank capacity shall be approx. 15 m3
   2x100% (one duty, one standby) vertical pumps shall be provided to pump out the liquid from the slop tank to the oily water system.


       The pumps shall have level controlled start/stop to drain out the slop tank automatically and shall have protection against dry running.
     The pumps shall conform to the owner.


  The capacity of the pump shall be sufficient to prevent tank overflow in any operational scenario.
     The tank shall at least be provided with a level gauge, level switches, overflow and drain connections, and a truck-out connection beside vents, a manhole, and an opening for pump installation.


        The pumps shall be provided with check valves, isolation valves, and a local pressure gauge at the outlet.
      The material of the pump shall be suitable to handle liquid hydrocarbons as well as water.


     Strainers shall be provided at the suction to protect pump internals against damage due to solid foreign matter.