power plant
Miscellaneous
Steel Structure, Platforms & Stairs
General
Steel structure and platforms shall be provided to facilitate easy access to all valves, equipment, instruments, etc. for operation and maintenance.
All main valves, meters, instruments, etc.
must be accessible from at least one side within man-height level.
The structure, platforms support, and walkways shall be fabricated in general compliance with 12-SAMSS-007.
A rigid, self-supporting structure, fabricated from appropriate
structural steel material shall be furnished. Welded construction shall be
employed throughout.
The structure,
platform grating, etc. shall be hot-dipped galvanized.
Minimum platform/walkway width shall be 1000 mm (3'-4").
The platform shall be
accessed via stairs unless otherwise approved.
Pad eye type lifting plates shall be provided for lifting the skid.
The lifting plates shall be designed and
located to enable lifting with equal weight distribution.
The skid structure, including in-place pipe and equipment, supports, shall be designed, fabricated, assembled
Skid structure
shall be designed of structural dead loads, water-filled pipe and equipment
loads and a 130 kph wind velocity.
All structural
steel shapes, bars, and plates shall conform to ASTM-A36, API 5L, Grade B or
ASTM A53, Grade B or ASTM A106, Grade B, unless specified otherwise.
Skid structure shall be fabricated and assembled within AISC tolerances.
All connections shall
be welded in accordance with AWS D1.1 and welds shall develop the full strength
of the member.
The structure, platforms etc
1st 12-SMSS-007
2nd 20-SMSS-001
3rd Occupational Safety and Health Act (OSHA)
4th American Welding Society (AWS)
5th American Institute of Steel Construction (AISC)
6th American Society for Testing Material (ASTM)
7th ASTM A-36 Standard Specification for Structural
Steel
8th ASTM A-488 Qualification of Procedures and
Personnel for the welding of steel castings.
Welding
General
All welding works shall be carried out in accordance with the latest edition of API standard 1104, ASMI Section-IX
The Contractor
shall be responsible for the quality of welding carried out by his organization
and shall conduct the tests of the welding procedure to determine its
suitability of ensuing welds which shall meet the requirement of the latest Saudi
Aramco standards.
The Contractor
shall also conduct the qualification tests of their welders and welding
operators to ensure that they are competent and qualified enough to achieve the
required quality.
The Contractor
shall maintain a record of the results obtained in welding procedure and welder
operator performance qualifications.
The welders
identification number or symbol shall be stamped near each executed welding.
ii. Welding Procedure Specifications (WPS)
1) The Contractor shall qualify the welding procedure specification by the welding of the specimens/test coupons according to the latest relevant.
2) The Contractor shall list the parameters applicable to welding that is performed in the construction of weldments built in accordance with the ASME Section IX
3) The Contractor
shall prepare “Weld Tables” in accordance with SAES-W-012, indicating line
designations, materials, thickness and welding process, etc.
4) The welding shall not commence until the WPS
5) All joints
shall be prepared according to the relevant standards.
6) Surfaces to be
welded, shall be free from oil, grease, foreign matter, corrosion products, and
humidity and shall be free from protective coatings as well.
7) Tack welds used to secure alignment shall be removed completely.
If tack welds are to be
incorporated into the final weld, their stopping and starting ends shall be
properly prepared by grinding, so that they may be satisfactorily incorporated
into the final weld, provided the tacks are not cracked and are made with the
same material and procedure as the main weld. Cracked tacks shall be removed
completely.
iii. Procedure Qualifications Record
The Contractor shall prepare and submit PQR for
each welding process on Saudi Aramco format as per SAES-W-012 to record all the
data, variables, results, etc. of weld test coupons.
iv. Non-Destructive Testing (NDT
1) The extent of
weld inspection, the final weld quality, and the method of examination shall be
carried out as per the latest related Saudi Aramco standards.
2) The Contractor
shall maintain adequately indexed records of all the welding, weld inspection, and repairs, which shall be available for the company representative.
c] Flanges, Gaskets, Bolts & Nuts
i. Flanges
1) The flanges, gaskets, bolts, and nuts shall conform
2) The flanges to
be used shall be forged carbon steel, weld neck, raised face type, with a class
matching the pressure rating of the relevant piping. Another type of flanges can
be used subject to Owner/Engineer’s specific approval based on acceptable
technical justification by the Contractor.
ii) Gaskets
1) The gasket to
be used shall conform standards including those mentioned above under Item (a), ASME B31.3, and ASME
B16.20.
2) The gaskets
shall be compatible with the flange facing, the strength of the flange, and bolting.
3) The gaskets to
be used shall be spiral wound type 316 stainless steel winding, flexible
graphite filled, with carbon steel guide ring as per ASME B16.20 for raised
face flanges.
Another type of gaskets can be used upon specific approval by
Owner/Engineer based on acceptable technical justification by the Contractor.
iii) Bolting
1) Bolting for
flanged joints shall conform to all the relevant Saudi Aramco standards, ASME
B16.5, and ASME B16.47.
2) The material
shall be ASME A193 grade B7 stud bolts with ASTM A194 grade 2H nuts, unless
otherwise approved by Owner/Engineer on acceptable technical justification by
the Contractor.
3) Washers shall
be provided in accordance having material
compatible with bolting and the flange.
4) Special washers and kits shall be used where necessary, such as insulating flanges, in conformance
5) The bolt
tightening shall be in conformance with the sequence and torque specified in
SAES-L-050.
d] Traps
i. Automatic traps will be provided to automatically drain out the liquid from the gas lines and equipment,
ii. The traps material shall be suitable to handle
liquid hydrocarbons and water.
iii. The traps shall be provided with isolating
valves and a bypass valve to facilitate maintenance and manual drainage.
iv. The outlet of the traps shall be led to the
slop tank.
e] Sampling System
i. Gas samples are required to be taken to
determine the gas composition, relative density, and BTU content. Samples shall
be collected at least once a week using automatic gas samplers.
ii. Sample collection control systems shall be time-based in sampling rate. The sample rates of volumes shall be unaffected by
variances in pipeline or sample cylinder pressures or temperatures.
iii. ANSI 316 stainless steel sampler probes 1/8
inch or 1/4 inch diameter tubing and of the single tube or dual pitot tube
configuration shall be used. For pipes up to 12-inch size, the probe trips
shall be located near the center of the pipe and for pipe larger than to 12 inches in
size, the probe tip shall be at least 1/6th of the pipe's internal diameter.
iv. Constant pressure sample cylinders shall be
used.
f] Burn Pit/Flare System and Ignitors
i. Burn pit(s)/flare systems of adequate size
shall be provided, standards, for disposal of
vented gas and hydrocarbon waste through burning.
ii. A suitably designed ignitor shall be provided
to ignite the pilot gas, which in turn ignites the vented gas and waste.
iii. The system shall comprise all the necessary
equipment, instruments required for the smooth, reliable, and safe operation of the
system.
iv. The location of the burn pit/flare system shall
be at a safe distance from the main equipment to preclude any fire hazard.
v. The Contractor shall propose a flare in place
of the burn pit, as an option, for burning of gases for Aramco approval.
g] Nitrogen Purging System
i. Purging of lines for maintenance and other
activities shall be carried out by the use of Nitrogen gas.
ii. Contractor shall supply a complete Nitrogen gas system comprising of Nitrogen tank/cylinders, pressure gauges, pressure
regulators, storing facilities with proper sheds and appropriate connections
dedicated to respective equipment and interconnection piping.
iii. Nitrogen purge connections shall be provided at
suitable locations with the approval of the Owner/Engineer.
h] Utility System
i. Potable water and other utilities, as necessary, for the facilities at RPP-10 end shall be extended from RPP-10 installation of the system(s) and it shall be carried out in compliance
ii. A hose reel station with a rubber hose of at At least 40m in length with quick coupling shall be provided.
iii. At shall be made to hook up the tanker trucks for the supply of potable water as required.
i] Data Sheets
Reference is made to the forms of Bidder’s Data Sheets of these Specifications. The blank forms
contained therein shall be
completely filled in and submitted together with the Bid.