Fire detection System - Fire Extinguishing System for Outdoor Power Transformers

 



DESIGN

 

     Outdoor transformers shall be separated from each other by fireproof walls.

    To prevent or reduce fire in case of an oil spill, transformer oil collection pits shall be provided.

 The outdoor transformer station shall be equipped with efficient fire detection and extinguishing system.

 

   Fire detection System

 

-         The transformer station shall be equipped with an efficient fire fighting, complete with a pressurized water tank sufficient for one 125 MVA or one 25MVA transformer but not less than 40m3 , 20m3 respectively.

-         Time required for extinguishing fire of one transformer 25MVA shall not exceed 2 minutes.

-         Duration of water sprinkling shall be 5 minutes.

-         The detection systems in any transformers shall instantaneously come into action in case of a fire isolating the transformer by tripping the transformers circuit breakers from both sides and put a fire extinguishing system into action.

-         A number of detectors shall be suitable for the transformer and mounted at the cover level of the transformer. The detectors shall detect any amount of abnormal temperature rise generated by a fire on the transformer tank, or the terminals, or even on the transformer's bed.

 

-         The detectors shall be designed and equalized such that they do not operate at slow temperature rise which may occur due to variation of load, ventilation, solar effect…etc and shall ensure complete security such that it will not be operated due to any reason except fire.

 

-         The detectors shall be connected in series by a fire-resistance cable which is connected to detection unit and the detectors shall be simple, study inspects vibration proof and moisture acid resistant construction.

-         A double detection system shall be designed in order to prevent the activation of the extinguishing system due to false indication.

-         In order to prevent the activation of the system due to false indication, the detection system is doubled with one piping system pressurized by air and with thermo activated nozzle and with one electric differential thermal activated system the water the spray system is activated only when a fire detection signal is given from the two detection system at the same time. The activated system shall be indicated in a control unit and activate in the area fire alarm signal.

-         Provision shall be made for a guard current flowing through the detectors. Interruption of the guard current due to the breaking of the elements series connecting cable or load terminal shall activate an audible and visible alarm signal at the detection unit of the equipment indicating interruption of guard current. This alarm signal must not activate the extinguishing system and the signal can be used for blocking the extinguishing system if needed.

 

   Fire Extinguishing System for Outdoor Power Transformers

 -         In order to extinguish a fire in the shortest possible time, the transformer shall be provided with a high-velocity water spray system. The water spray system shall be provided as a conventional system with pressurized water in the tubes and crown, pressure, and closed spray nozzles or as an empty system with an open spray nozzle. Any provided system shall fulfill the regulations in the following:-

·                 High-velocity water spray system for transformer system design and installation instructions (automatic sprinkler corps of America).

·                 NEPA15 water spray fixed systems for fire protection association inc./ USA)

 

-         This system consists of two cages of tubes surrounding the periphery of the transformer at suitable distance apart.

-         The cages shall be supported and held in place by a re-fixed pipe arrangement, and the part of the cage at the side of the running rail shall be disconnectable.

-         One of the two cages shall be fixed at the height of the transformer cover and the other at a height straight above the transformer bed.

-         The cages shall consist of prefabricated parts which are hot-dip galvanized after forming and mounting on spot without damaging the galvanization.

-         Each cage shall be equipped with judiciously directed spray nozzles having sufficient number to ensure complete flooding and coverage of the transformer by means of sprayed water. The nozzles shall be protected with caps arranged to blow off when nozzles operate.

-         This system consists of tubes, pipes and nozzles, when a fire is detected a deluge valve are opened and the whole system with its open spray nozzles is activated.

-         Automatic deluge valve assembly should be complete with pressure switches, pressure gauge, drain and test valve, site drainage system, etc. The site drainage system should be designed to clear the water discharged from the drain and test valve during periodic tests. An automatic deluge valve simply should be protected from adverse environmental conditions.

 

           Function

 

Power transformers water spray fire extinguishing system shall comprise as in a schematic diagram an air pressure water tank has an insulating air cushion in order to protect the transformer in case of fire without electric energy. As temperature control, melting nozzles are installed inside the pressure activator line on the transformer. In case that the temperature limit is exceeded, the melting nozzles break and the air in the activator line escapes. Due to this sudden pressure drop, the valve station (deluge valve) opens immediately.

 

The insulating The water tank pushes the water out of the air pressure water tank through the deluge valve into the spraying cage. Which is assembled on the transformer.

 

The air pressure and the water level inside the water tank are continuously controlled and automatically filled up by appropriate devices.

 

The manual operation is carried out with an excitation valve in the valve station causing the same action achieved by the separate excitation air pipeline in the automatic operation. Push buttons for manual operation shall be completely secured against the unauthorized operation and accidental system operation. Automatic deluge valve assembly shall be complete with pressure switches, pressure gauges, drain and test valve, site drainage system… etc. Site the drainage system should be designed to clear the water discharged from the drain and test valve during periodic tests, and the automatic deluge valve assembly shall also be protected from adverse environmental conditions.

 

       Air Pressure Water Tank

 

-         The water supply shall consist of storage vessel put under pressure by pressurized air.

-         The water storage vessel shall be externally and internally galvanized  with an anti-corrosion coat approved by a qualified organization and tested at a pressure not less than 150% of the operating pressure.

-         The storage vessel shall be equipped with filling, inlet, discharge outlet, discharge pipe in the direction of the pressure of the spraying cage, and a pipe in direction of compressed air.

-         The water pressure shall be sufficient to charge the water vessel to the specified pressure within a time not more than 3 hours.

-         The capacity of the storage of the vessel shall be sufficient to maintain flooding of the biggest transformer for a time not less than stated in standards and regulations.

-         The water pressure system shall be a dual system one in operation and the other is standby. Each one should have its own control, protection supply, etc., and will be adjusted on operation mode or standby mode by a selector switch.

-         Push buttons for manual operation shall be completed secured against an unauthorized operation and the accidental system, technical specification for systems components, and mounting as stated in the regulations should be submitted with tender standby, system should comprise the following:-

·                 Air, compressor complete with driving units.

·                 Pump complete with driving unit.

 

The water pressure shall meet the requirements of  efficient operation of spraying nozzles.

 

        Spraying Cage for Transformers

 

The cage is self-supporting and shall not be fixed on transformers, the cage can easily be opened. The water spray system will be released automatically by bursting one of the glass bulb sprinklers which causes a pressure loss in the pneumatic incitation pipe, together with a signal from the electrical detection system. By these two actions, the deluge valve concerned will be opened and the water can flow towards the nozzles installed in the spray cage to flood the transformer.

 

           Electrical / Control For Automatic Process

The control cabinet shall be with a degree of protection IP54, the signal from automatic fire detection system shall be received by the fire alarm control panel, heat dissipated shall be controlled by a thermostat. CPU and the control shall include air pressure, water refill, and run dry safety device of the filling pump.

 

 TESTING

 

If the supplier has carried out type tests on the offered equipment in the last ten years according to the relevant standard then the supplier shall provide type test certificates for the approval of the owner, otherwise type tests have to be carried out in the presence of the owner.

 

 

 ACCEPTANCE AND REJECTION

 

The supplier shall forward to the purchaser, three copies of certificates proving that all tests required have been carried out and also samples & catalogs of the equipment.

 

 SPARE PARTS

 

            List of manufacturer’s recommended spare parts shall be included in addition to spare parts requested by the purchaser if required.

 

 GUARANTEE

 

            The supplier shall guarantee fire fighting equipment against design, material, and manufacturing defects for a period as given in tender documents.

 

 SUBMITTALS

 

            Required Submittals:-

 -         The number of documents required under this clause shall be three (3) in all cases.

-          The supplier shall complete and return on three (3) copies of all schedules are attached to this specification.

-         A list of international / national codes and standards specification covering raw material, components, test procedures, etc and a list of tests normally carried out on material and a description of test equipment used shall be supplied.

-         A short description of manufacturing processes and equipment employed for production shall be provided.

-         Detailed physical, characteristics and electrical drawings.

-         Dimensioned drawings of complete equipment and its detailed components with a brief description of erection and maintenance requirements.

-         Fully detailed type test reports.

-         Details of routine tests to which all units will be tested before dispatch.

-         Supplier’s recommended training requirements for purchaser’s staff.

 

  DELIVERY

 

The manufacture shall be responsible for and shall repair or replace at his own expense any and all damaged equipment where damage was due to improper preparation for supply.

  

 REFERENCE LIST

  The tenderer shall submit a reference the list that the proposed equipment has been in successful operation in an integrated system on three different substations of same or higher capacity outside country of the manufacturer and/or in EEHC network for a period not less then three years during the last ten years.

 The experience of the manufacturer and the sub-manufacturer shall be evaluated on the above basis.